VYAS BUILDCON PVT. LTD.: RERA track record
CIN U45200PN2010PTC135713 · Company · attribution by exact filing name, entity resolution in progress
VYAS BUILDCON PVT. LTD. has 8 registrations on MahaRERA, including AISHWARYA RESIDENCY and PRATIBHA SADAN CO. OP. HSG. SOC.. Its filings disclose 5 earlier MahaRERA projects: declares 4 of 5 past projects completed on time.
Projects by this developer
Showing all 8 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| Anudatta CHSP52100079237 | Rambaug Colony, Pune, 411038 | 54 | 4% | 18 Feb 2025 | Registered |
| 31 IDEAL CO OP HSG SOCP52100047442 | IDEAL COLONY, Pune, 411038 | - | - | 31 Oct 2022 | Registration lapsed |
| AASAWARI CO. OP. HSG.SOCIETYP52100024235 | IDEAL COLONY, Pune, 411038 | - | - | 27 Jan 2020 | Completed |
| AISHWARYA RESIDENCYP52100002455 | Baner, Pune, 411045 | - | - | 1 Aug 2017 | Completed |
| ALANKAPURISHREE CO.OP.HSG.SOC.LTD.P52100018752 | RAMBAUG COLONY, Pune, 411038 | - | - | 30 Nov 2018 | Completed |
| PRATIBHA SADAN CO. OP. HSG. SOC.P52100002624 | Kothrud, Pune, 411038 | - | - | 2 Aug 2017 | Completed |
| SUDHENDU CO OP HSG SOCIETYP52100029983 | RAMBAUG COLONY, Pune, 411038 | - | - | 20 Jul 2021 | Completed |
| SWAPNALI CO OP HSG SOCP52100049943 | OPPOSITE KARISHMA SOCIETY, Pune, 411038 | - | - | 6 Mar 2023 | Registration lapsed |
What this promoter declares as its own experience
VYAS BUILDCON PVT. LTD. declares experience on 5 earlier projects. One carries a registration number we could match on MahaRERA, under this promoter's own name.
One of these declarations can be compared with the dates that project's own registration holds. It gives the same original completion date that registration holds.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| AISHWARY RESEDENCY | 17 Oct 2017 | 18 Jul 2018 | +9 months |
| Alankapurishree CHS | 30 Jun 2022 | 20 Aug 2021 | On time |
| Aasawari CHS | 30 Dec 2023 | 18 May 2022 | On time |
| SUDHENDU CO OP HSG SOCIETY P52100029983 | 30 Apr 2024 | 15 Feb 2024 | On time |
| Sudhendu CHS | 30 Apr 2024 | 25 Jan 2024 | On time |
Frequently asked questions
How do I verify VYAS BUILDCON PVT. LTD. as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U45200PN2010PTC135713 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with VYAS BUILDCON PVT. LTD.?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.