VARAD RAJA REALTY: RERA track record
GSTIN 27AAWFV5243Q1Z1 · Partnership · attribution by exact filing name, entity resolution in progress
VARAD RAJA REALTY has 1 registration in this build, including VIJAYSHREE CHSL. Its filings disclose 3 earlier MahaRERA projects: 3 of 3 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| VIJAYSHREE CHSL | Thane, Maharashtra | 29 | 17% | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Satishdham Co-operative Housing Society LTD P51700031050 | 13 Jan 2024 | 13 Jan 2024 | On time |
| PRARTHANA COOPERATIVE HOUSING SOCIETY LTD P51700034612 | 17 Feb 2025 | 17 Feb 2025 | On time |
| SAROJ SADAN CHS LTD P51700050057 | 19 Jan 2026 | 19 Jan 2026 | On time |
Frequently asked questions
How do I verify VARAD RAJA REALTY as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27AAWFV5243Q1Z1 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with VARAD RAJA REALTY?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.