The Kings Way AOP: RERA track record

Others ยท attribution by exact filing name, entity resolution in progress

The Kings Way AOP has 2 registrations in this build, including The Kings Way - A1, A2 and A3 and THE KINGS WAY AOP EWS. Its filings disclose 8 earlier MahaRERA projects: 0 of 6 past projects completed on time.

2Registrations in this build
8Past projects disclosed
+22 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
The Kings Way - A1, A2 and A3Pune, Maharashtra--Completed
THE KINGS WAY AOP EWSPune, Maharashtra--Registration lapsed

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Venkatesh Flora
31 Mar 20076 Oct 2008+18 months
VENKATESH FLORA
1 Mar 201113 Jun 2013+27 months
GRAN EXITO
1 Sep 201226 Jul 2016+47 months
Gran Exito
30 Sep 20129 Feb 2015+28 months
Casa Familia
31 Dec 20169 Jan 2017On time
CASA FAMILIA
31 Dec 20161 Sep 2017+8 months
The Kings Way - A1, A2 and A3
P52100003300
31 Dec 2024Not completed yetOngoing
THE KINGS WAY AOP EWS
P52100031169
31 Dec 2024Not completed yetOngoing

Frequently asked questions

How do I verify The Kings Way AOP as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with The Kings Way AOP?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.