Shri Sati Builders and Developers Private Limited: RERA track record
CIN U45200MH1991PTC062340 · GSTIN 27AAACS5793H1Z0 · Company · attribution by exact filing name, entity resolution in progress
Shri Sati Builders and Developers Private Limited has 4 registrations on MahaRERA, including Anand Bhavan - Pristino and Mannat Tower. Its filings disclose 4 earlier MahaRERA projects: declares 0 of 4 past projects completed on time.
Projects by this developer
Showing all 4 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| Girivan VarenyaaPR1180002601861 | Ghatkopar, Mumbai Suburban, 400077 | 32 | 0% | 10 Sep 2026 | Registered |
| Anand Bhavan - PristinoP51800008855 | Kurla, Mumbai Suburban, 400071 | - | - | 19 Aug 2017 | Completed |
| Girivan ShivkunjP51800011754 | Chembur, Mumbai Suburban, 400071 | - | - | 31 Aug 2017 | Completed |
| Mannat TowerP51800009212 | Kurla, Mumbai Suburban, 400075 | - | - | 22 Aug 2017 | Completed |
What this promoter declares as its own experience
Shri Sati Builders and Developers Private Limited declares experience on 4 earlier projects. 3 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
3 of these declarations can be compared with the dates those projects' own registrations hold. On 2, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. It changes nothing about whether those projects were delivered on time.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Girivan Paramjyoti | 7 Feb 2017 | 1 Jul 2017 | +5 months |
| Anand Bhavan - Pristino P51800008855 | 30 Sep 2018 | 28 Feb 2019 | +5 months |
| Mannat Tower P51800009212 | 31 Mar 2019 | 4 Nov 2019 | +7 months |
| Girivan Shivkunj P51800011754 | 31 Mar 2020 | 28 Jun 2021 | +15 months |
Frequently asked questions
How do I verify Shri Sati Builders and Developers Private Limited as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U45200MH1991PTC062340 and GSTIN 27AAACS5793H1Z0 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Shri Sati Builders and Developers Private Limited?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.