SHREESWAMI CONSTRUCTIONS: RERA track record

GSTIN 27ABGPK0598J1ZB · Others · attribution by exact filing name, entity resolution in progress

SHREESWAMI CONSTRUCTIONS has 3 registrations on MahaRERA, including SHREEBRAMHAND and SHREEMALHAR APARTMENT. Its filings disclose 8 earlier MahaRERA projects: declares 8 of 8 past projects completed on time.

3RERA registrations
8Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation
Follow this developer. An email when SHREESWAMI CONSTRUCTIONS registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 3 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
SHREEBRAMHANDP51600030062RTO COLONY BODHALE NAGAR NASHIK, Nashik, 42201111881%29 Jul 2021Registration lapsed
SHREESAFALYA APARTMENTPR1220002601367KARMYOGI NAGAR, Nashik, 422009520%30 Jul 2026Registered
SHREEMALHAR APARTMENTP51600048639GANGAPUR ROAD, Nashik, 4220131242%10 Jan 2023Completed

What this promoter declares as its own experience

SHREESWAMI CONSTRUCTIONS declares experience on 8 earlier projects. 7 of them carry a registration number we could match on MahaRERA, of which 5 are registered under a different promoter name.

7 of these declarations can be compared with the dates those projects' own registrations hold. On 2, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. That changes the arithmetic on 2 of the 7 completions recorded here as on time: measured against the original deadline the register itself holds, those were finished after it. A completion date is also recorded against 1 registration MahaRERA does not show as completed. A registration lapses when a promoter files neither a completion nor an extension, so that can mean the completion was never filed rather than that the project was not finished.

Declared projectRegistered toStatus
SHREENIWAS APARTMENTKRISHNA CONSTRUCTIONCompleted
SHREENAVSHAKTI APARTMENTSWAMI CONSTRUCTIONSCompleted
SHREENEELKANTH APARTMENTSWAMI CONSTRUCTIONSCompleted
SHREESAMRUDDHI PARKSWAMI CONSTRUCTIONSCompleted
SHREEVISHWASWAMI CONSTRUCTIONSCompleted

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
SHREEVISHWA
30 Dec 202012 Jul 2020On time
SHREEVISHWA
P51600008780
30 Dec 202015 Sep 2019On time
SHREENIWAS APARTMENT
P51600022902
30 Jun 202217 Jan 2022On time
SHREENAVSHAKTI APARTMENT
P51600022623
30 Sep 202214 Oct 2021On time
SHREESAMRUDDHI PARK
P51600025875
30 Dec 202322 Sep 2022On time
SHREENEELKANTH APARTMENT
P51600045701
31 Mar 202529 Nov 2024On time
SHREEMALHAR APARTMENT
P51600048639
31 Dec 202526 Aug 2025On time
SHREEBRAMHAND
P51600030062
31 Mar 202614 Oct 2025On time

Frequently asked questions

How do I verify SHREESWAMI CONSTRUCTIONS as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27ABGPK0598J1ZB on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with SHREESWAMI CONSTRUCTIONS?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.