Home / Developers / SHREE VENKATESH DEVELOPERS
SHREE VENKATESH DEVELOPERS: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
SHREE VENKATESH DEVELOPERS has 6 registrations in this build, including SAI SANKUL PHASE-II and TIRUMALLA GLORY. Its filings disclose 11 earlier MahaRERA projects: 11 of 11 past projects completed on time. Litigation is declared on 1 of its registrations.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| SAI SANKUL PHASE-II | Aurangabad, Maharashtra | - | - | Completed |
| TIRUMALLA GLORY | Nashik, Maharashtra | - | - | Completed |
| Venkatesh Graffiti Elite Phase 1 | Pune, Maharashtra | - | - | Completed |
| VENKATESH GRAFFITI ELITE PHASE 2 | Pune, Maharashtra | - | - | Completed |
| Shree Venkatesh Heights | Nashik, Maharashtra | - | - | Completed |
| VENKATESH VIOM | Pune, Maharashtra | 87 | 97% | Completed |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| TIRUMALLA HILLS | 31 Dec 2013 | 30 Dec 2013 | On time |
| VENKATESH SHARVIL | 31 Mar 2014 | 9 Jul 2013 | On time |
| VENKATESH BILVA | 31 Dec 2014 | 24 Jul 2014 | On time |
| VENKATESH LAKE VISTA | 31 Dec 2015 | 25 Dec 2015 | On time |
| VENKATESH GRAFFITI PHASE 1 | 31 Jul 2017 | 10 Apr 2017 | On time |
| VENKATESH JOYNEST PHASE 1 | 31 Jul 2017 | 10 Mar 2017 | On time |
| VENKATESH GRAFFITI PHASE 7 | 31 Mar 2018 | 25 Jan 2018 | On time |
| VENKATESH JOYNEST PHASE 2 | 31 May 2018 | 9 Feb 2018 | On time |
| VENKATESH LAKE LIFE PHASE 1 | 30 Jun 2018 | 28 Jun 2018 | On time |
| VENKATESH GRAFFITI PHASE 2 | 31 Dec 2018 | 25 Jan 2018 | On time |
| Shree Venkatesh Pride | 31 Dec 2020 | 14 Jul 2020 | On time |
Frequently asked questions
How do I verify SHREE VENKATESH DEVELOPERS as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with SHREE VENKATESH DEVELOPERS?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make SHREE VENKATESH DEVELOPERS unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.