Shhraddha Properties: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

Shhraddha Properties has 3 registrations in this build, including Shhraddha Ellegance Building B and Shhraddha Ellegance Building C. Its filings disclose 8 earlier MahaRERA projects: 3 of 8 past projects completed on time.

3Registrations in this build
8Past projects disclosed
+2 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Shhraddha Ellegance Building BSolapur, Maharashtra--Completed
Shhraddha Ellegance Building CSolapur, Maharashtra--Completed
SHHRADDHA ELLEGANCE BUILDING HSolapur, Maharashtra3234%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Shhraddha Ashray
15 Sep 201313 Sep 2013On time
Bhramhapuri Society
31 Mar 201619 Jul 2016+4 months
Brahmapuri Society
31 Mar 201619 Jul 2016+4 months
Shhraddha Ellegance Building A
30 Jun 20166 Oct 2016+3 months
Shhraddha Ellegance Building K
31 Oct 20166 Oct 2016On time
Shhraddha Ellegance Building G
31 Dec 201623 Jan 2017+1 months
Shhraddha Ellegance Building C
31 Dec 20182 Nov 2017On time
Shhraddha Ellegance Building B
31 Dec 201915 Jun 2021+18 months

Frequently asked questions

How do I verify Shhraddha Properties as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Shhraddha Properties?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.