ReraGenieLog inGet a buyer report

Home / Developers / SHETH INFRAWORLD PRIVATE LIMITED

SHETH INFRAWORLD PRIVATE LIMITED: RERA track record

Company ยท attribution by exact filing name, entity resolution in progress

SHETH INFRAWORLD PRIVATE LIMITED has 1 registration in this build, including SHETH MIDORI. Its filings disclose 10 earlier MahaRERA projects: 2 of 10 past projects completed on time.

1Registrations in this build
10Past projects disclosed
+5 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
SHETH MIDORIMumbai Suburban, Maharashtra--Completed

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
VASANT GARDEN
31 Mar 20071 Dec 2007+8 months
VASANT VALLEY
30 Jun 20109 Dec 2010+5 months
VASANT GALAXY
31 Oct 201030 Mar 2011+5 months
CYNERGY
8 Sep 20118 Sep 2011On time
VASANT MARVEL
31 Oct 201112 Jul 2012+8 months
BEAUMONDE
31 Dec 201110 Jan 2012On time
VASANT LAWNS
31 Mar 201212 Nov 2012+7 months
VIVIANA MALLS
9 May 20139 May 2013On time
SIGMA
30 Jul 201415 Dec 2014+5 months
SHETH MIDORI
P51800000882
31 May 201931 Dec 2022+43 months

Frequently asked questions

How do I verify SHETH INFRAWORLD PRIVATE LIMITED as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with SHETH INFRAWORLD PRIVATE LIMITED?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.