Home / Developers / SAI SHRADDHA DEVELOPERS
SAI SHRADDHA DEVELOPERS: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
SAI SHRADDHA DEVELOPERS has 10 registrations in this build, including SAI SHRADDHA DEVELOPERS and ANUJ RESIDENCY. Its filings disclose 8 earlier MahaRERA projects: 7 of 8 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| SAI SHRADDHA DEVELOPERS | Ahmednagar, Maharashtra | - | - | Registration lapsed |
| ANUJ RESIDENCY | Aurangabad, Maharashtra | - | - | Registration lapsed |
| SAI ICON | Thane, Maharashtra | - | - | Registration lapsed |
| EXCELLENCE RESIDENCY 1 | Palghar, Maharashtra | - | - | Registration lapsed |
| SAI DARSHAN | Pune, Maharashtra | - | - | Completed |
| MERITON TOWERS | Pune, Maharashtra | - | - | Registration lapsed |
| SAI DARSHAN PHASE II | Pune, Maharashtra | 48 | 33% | Registered |
| SHIV HEIGHTS | Nashik, Maharashtra | 41 | 46% | Completed |
| Sai Shraddha Phase II | Raigarh, Maharashtra | 70 | 16% | Registered |
| SAI ICON TYPE B | Thane, Maharashtra | 258 | 2% | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| RAHUL RESIDENCY | 16 Nov 2013 | 16 Nov 2013 | On time |
| SAI SUPER MARKET | 30 Nov 2013 | 30 Nov 2013 | On time |
| SAI PLAZA B WING | 10 Apr 2015 | 10 Apr 2015 | On time |
| SAI PLAZA A WING | 27 Jul 2017 | 27 Jul 2017 | On time |
| Aishwariya Trade centre | 26 Aug 2018 | 26 Aug 2020 | +24 months |
| LAMELOSA | 26 Nov 2020 | 26 Nov 2020 | On time |
| SAI DARSHAN | 30 Sep 2023 | 30 Sep 2023 | On time |
| SAI ICON P51700020449 | 30 Dec 2023 | 17 Feb 2023 | On time |
Frequently asked questions
How do I verify SAI SHRADDHA DEVELOPERS as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with SAI SHRADDHA DEVELOPERS?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.