S. RAHEJA LOFTS LLP: RERA track record
GSTIN 27AEOFS6962F1ZF · Others · attribution by exact filing name, entity resolution in progress
S. RAHEJA LOFTS LLP has 1 registration in this build, including AVISA BY S RAHEJA. Its filings disclose 9 earlier MahaRERA projects: 4 of 9 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| AVISA BY S RAHEJA | Mumbai Suburban, Maharashtra | - | - | Registration lapsed |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| RAHEJA PRIME | 1 Jan 2014 | 1 Apr 2014 | +3 months |
| HARI BHUVAN | 1 Aug 2015 | 1 Sep 2015 | +1 months |
| NATRAJ MADHU PARK | 1 Oct 2016 | 1 Aug 2016 | On time |
| GURUKRIPA KALINA NAPHANAGAR CHSL | 1 Oct 2016 | 1 Oct 2016 | On time |
| SANTACRUZ SAPPHIRE | 30 Apr 2017 | 1 Jul 2017 | +2 months |
| SHREE POOJA VII | 1 Nov 2017 | 28 Feb 2018 | +4 months |
| SDS RAHEJA RESIDENCY | 31 Jan 2018 | 31 Mar 2018 | +2 months |
| HINDUJA HOSPITAL S-2 | 1 Dec 2018 | 1 Dec 2018 | On time |
| NEW LIGHT P51800024620 | 30 Dec 2025 | 14 Dec 2022 | On time |
Frequently asked questions
How do I verify S. RAHEJA LOFTS LLP as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27AEOFS6962F1ZF on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with S. RAHEJA LOFTS LLP?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.