Ranco Realty Pvt Ltd: RERA track record
Company ยท attribution by exact filing name, entity resolution in progress
Ranco Realty Pvt Ltd has 7 registrations on MahaRERA, including Bapusaheb Nadkarni Nagar and Swami Samarth Nagar. Its filings disclose 19 earlier MahaRERA projects: declares 19 of 19 past projects completed on time.
Projects by this developer
Showing all 7 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| Yashoday Phase OneP52900012395 | near sawantwadi railway station, Sindhudurg, 416510 | 34 | 85% | 1 Sep 2017 | Completed |
| Yashoday Nagar Phase IIIP52900012930 | Niravade, Sindhudurg, 416510 | 24 | 0% | 7 Sep 2017 | Completed |
| Bapusaheb Nadkarni NagarP52900004637 | Niravade, Sindhudurg, 416510 | 20 | 5% | 9 Aug 2017 | Completed |
| Yashoday Phase IVP52900025579 | behind kokan crown resort, Sindhudurg, 416510 | 16 | 0% | 1 Jul 2020 | Registration lapsed |
| Swami Samarth NagarP52900012388 | Malgaon, Sindhudurg, 416510 | 7 | 0% | 1 Sep 2017 | Completed |
| Swami Samarth Nagar Survey No. 133 Hissa No. 3P52900049565 | Sawantwadi railway station, Sindhudurg, 416510 | 1 | 0% | 15 Feb 2023 | Registered |
| Yashoday Nagar Phase IIP52900013346 | Niravade, Sindhudurg, 416510 | 1 | 0% | 22 Sep 2017 | Completed |
What this promoter declares as its own experience
Ranco Realty Pvt Ltd declares experience on 19 earlier projects. None of them carries a registration number we could match on MahaRERA, which is usual for work done before the register existed.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Mohor | 15 Dec 2017 | 8 Jun 2016 | On time |
| Swami Samarth Nagar 1 | 2 Feb 2018 | 25 Dec 2016 | On time |
| Swami Samarth Nagar 2 | 2 Feb 2018 | 31 Mar 2017 | On time |
| Swami Samarth Nagar 3 | 2 Feb 2018 | 25 Feb 2017 | On time |
| Swami Samarth Nagar 5 | 2 Feb 2018 | 4 Jan 2017 | On time |
| Swami Samarth Nagar 7 | 2 Feb 2018 | 25 Feb 2017 | On time |
| Swami Samarth Nagar 11 A | 2 Feb 2018 | 24 Nov 2016 | On time |
| Swami Samarth Nagar 11 B | 2 Feb 2018 | 16 Dec 2016 | On time |
| Swami Samarth Nagar 12 | 2 Feb 2018 | 31 Mar 2017 | On time |
| Swami Samarth Nagar 14 | 2 Feb 2018 | 6 Sep 2016 | On time |
| Swami Samarth Nagar 15 | 2 Feb 2018 | 22 Sep 2015 | On time |
| Swami Samarth Nagar 16 | 2 Feb 2018 | 10 Jan 2017 | On time |
Frequently asked questions
How do I verify Ranco Realty Pvt Ltd as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Ranco Realty Pvt Ltd?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.