ReraGenieLog inGet a buyer report

Home / Developers / PRITHVI EDIFICE PVT LTD

PRITHVI EDIFICE PVT LTD: RERA track record

Company ยท attribution by exact filing name, entity resolution in progress

PRITHVI EDIFICE PVT LTD has 4 registrations in this build, including Prithvi Presidio, Buiding B, Phase-1 and PRITHVI PROXIMUS. Its filings disclose 1 earlier MahaRERA project: 0 of 1 past projects completed on time.

4Registrations in this build
1Past projects disclosed
+10 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Prithvi Presidio, Buiding B, Phase-1Pune, Maharashtra--Registration lapsed
PRITHVI PROXIMUSPune, Maharashtra22097%Registration lapsed
Prithvi Presidio, Building B, Phase-2Pune, Maharashtra--Registration lapsed
DOCTOR HOUSEPune, Maharashtra838%Registration lapsed

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
PRITHVI PRESIDIO A Building
30 Jun 201629 Apr 2017+10 months

Frequently asked questions

How do I verify PRITHVI EDIFICE PVT LTD as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with PRITHVI EDIFICE PVT LTD?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.