PARTH DEVELOPERS: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

PARTH DEVELOPERS has 11 registrations on MahaRERA, including PARTH ENCLAVE E BUILDING and PARTH CLASSIC. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 1 past projects completed on time.

11RERA registrations
2Past projects disclosed
+4 monthsMedian delivery slip
0Registrations with litigation
Follow this developer. An email when PARTH DEVELOPERS registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 11 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
SHREE JALARAM VATIKAP50500034073SOMALWADA, Nagpur, 4400253972%24 Mar 2022Registered
BHAGAT PARTH SERENITYP52000054454KAMOTHE, Raigarh, 4102063757%25 Jan 2024Registration lapsed
KosaladhishPM1190002600033Wanadongari, Nagpur, 441110200%7 Apr 2026Registered
AMAR SERENITY WING E LIG/MIG BUILDINGP52100018202PASHAN, Pune, 411045--15 Oct 2018Completed
BHAGAT HERITAGEP52000016262KAMOTHE, Raigarh, 410206--2 May 2018Completed
M/S SHRI SAI LATA FLAT OWNERS CO-OP HSG SOC LTDP51800032481CHAMBUR, Mumbai Suburban, 400089--10 Jan 2022Registration lapsed
PARTH CLASSICP52100013837Pimpri Chinchawad (M Corp.), Pune, 412105--27 Oct 2017Completed
PARTH ENCLAVE BUILDING FP52100025566KARVE NAGAR, Pune, 411052--28 Jun 2020Completed
PARTH ENCLAVE E BUILDINGP52100000678KARVE NAGAR, Pune, 411005--19 Jul 2017Completed
Parth VaibhavP51800013396Borivali, Mumbai Suburban, 400097--4 Oct 2017Registration lapsed
RENUKA PRIDEP51500047868VISHAL NAGAR, Aurangabad, 431005--1 Dec 2022Completed

What this promoter declares as its own experience

PARTH DEVELOPERS declares experience on 2 earlier projects. One carries a registration number we could match on MahaRERA, under this promoter's own name.

One of these declarations can be compared with the dates that project's own registration holds. It gives the same original completion date that registration holds.

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
PARTH JAINAM
31 Mar 201612 Aug 2016+4 months
SHREE JALARAM VATIKA
P50500034073
31 Mar 2027Not completed yetOngoing

Frequently asked questions

How do I verify PARTH DEVELOPERS as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with PARTH DEVELOPERS?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.