OM ENTERPRISES: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

OM ENTERPRISES has 10 registrations in this build, including VEER WAJEKAR COMPLEX-Phase 1 and SHREEMAN RESIDENCY. Its filings disclose 5 earlier MahaRERA projects: 2 of 4 past projects completed on time.

10Registrations in this build
5Past projects disclosed
+4 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
VEER WAJEKAR COMPLEX-Phase 1Raigarh, Maharashtra--Registration lapsed
SHREEMAN RESIDENCYThane, Maharashtra--Completed
MIRANDA RESIDENCYRaigarh, Maharashtra--Registration lapsed
CENTRAL PLAZAThane, Maharashtra--Completed
OM RESIDENCYPalghar, Maharashtra--Registration lapsed
SHREEMAN RESIDENCY B AND C WINGThane, Maharashtra3741%Registered
GIRIDHAR APARTMENTThane, Maharashtra3633%Registration lapsed
AKSHAY VISTAPune, Maharashtra7013%Registered
CENTER PLAZAThane, Maharashtra4349%Registered
VIGHNAHARTA HEIGHTRaigarh, Maharashtra1070%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
TARANGAN
30 Jun 201631 Mar 2017+9 months
SUNCITY
31 Dec 201630 Sep 2017+9 months
SHREEMAN RESIDENCY
31 Dec 201828 Dec 2018On time
MIRANDA RESIDENCY
28 Jun 202128 Jun 2021On time
GIRIDHAR APARTMENT
P51700045512
31 Dec 2025Not completed yetOngoing

Frequently asked questions

How do I verify OM ENTERPRISES as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with OM ENTERPRISES?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.