Home / Developers / OM CIVIL CONSTRUCTIONS
OM CIVIL CONSTRUCTIONS: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
OM CIVIL CONSTRUCTIONS has 5 registrations on MahaRERA, including RUKHMINI COMPLEX and UBHA VITEVARI. Its filings disclose 6 earlier MahaRERA projects: declares 4 of 5 past projects completed on time.
Projects by this developer
Showing all 5 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| JAY VITTHAL COMPLEX 1P52000078326 | DAPOLI, Raigarh, 410206 | 66 | 33% | 4 Dec 2024 | Registered |
| HARI VITTHALP52000030397 | Pushpak Node Vadghar, Raigarh, 410206 | - | - | 20 Aug 2021 | Registration lapsed |
| JAY VITTHAL COMPLEXP52000024742 | PUSHPAK, Raigarh, 410206 | - | - | 2 Mar 2020 | Completed |
| RUKHMINI COMPLEXP52000020689 | PUSHPAK VADGHAR, Raigarh, 410206 | - | - | 3 May 2019 | Completed |
| UBHA VITEVARIP52000022973 | NODE PUSHPAK, Raigarh, 410206 | - | - | 6 Nov 2019 | Completed |
What this promoter declares as its own experience
OM CIVIL CONSTRUCTIONS declares experience on 6 earlier projects. 3 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
3 of these declarations can be compared with the dates those projects' own registrations hold. Every one of them gives the same original completion date its registration holds. A completion date is also recorded against 1 registration MahaRERA does not show as completed. A registration lapses when a promoter files neither a completion nor an extension, so that can mean the completion was never filed rather than that the project was not finished.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| RUKHMAI COMPLEX | 31 Jan 2021 | 1 Jan 2021 | On time |
| UBHA VITHEVARI | 30 Oct 2021 | 15 Aug 2021 | On time |
| RUKHMINI COMPLEX P52000020689 | 30 Jan 2022 | 21 May 2021 | On time |
| JAY VITTHAL COMPLEX | 30 Jan 2022 | 1 Jan 2022 | On time |
| HARI VITTHAL P52000030397 | 31 Dec 2023 | 3 Apr 2025 | +15 months |
| JAY VITTHAL COMPLEX 1 P52000078326 | 31 Dec 2028 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify OM CIVIL CONSTRUCTIONS as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with OM CIVIL CONSTRUCTIONS?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.
Report an errorShare feedbackData from official MahaRERA filings. How we handle corrections is on the about page.