NANIS BUILDCON PRIVATE LIMITED: RERA track record
Company ยท attribution by exact filing name, entity resolution in progress
NANIS BUILDCON PRIVATE LIMITED has 8 registrations on MahaRERA, including VEDANT PERIDOT and VEDANT EMERALD PHASE 2. Its filings disclose 4 earlier MahaRERA projects: declares 3 of 4 past projects completed on time.
Projects by this developer
Showing all 8 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| VEDANT BERYLP50500033335 | SONEGAON, Nagpur, 440022 | 69 | 96% | 16 Feb 2022 | Completed |
| VEDANT AVENTURINEP50500080356 | JAITALA, Nagpur, 440036 | 41 | 10% | 26 May 2025 | Registered |
| VEDANT AQUAMARINEP50500055037 | Swagat Co-op Housing Society, Nagpur, 440025 | 36 | 58% | 26 Feb 2024 | Registered |
| VEDANT ONYXP50500077840 | SWAGAT CO-OP HOUSING SOCIETY, Nagpur, 440025 | 14 | 57% | 7 Nov 2024 | Registered |
| VEDANT EMERALD PHASE 2P50500012141 | Nagpur (M Corp.), Nagpur, 440022 | - | - | 1 Sep 2017 | Completed |
| VEDANT GARNETP50500023665 | The Swagat Co-operative Housing Society, Nagpur, 440023 | - | - | 24 Dec 2019 | Completed |
| VEDANT PERIDOTP50500009166 | Nagpur (M Corp.), Nagpur, 440022 | - | - | 19 Aug 2017 | Completed |
| VEDANT TANZANITEP50500027413 | SWAGAT CO-OP SOCIETY LAYOUT, Nagpur, 440023 | - | - | 8 Dec 2020 | Completed |
What this promoter declares as its own experience
NANIS BUILDCON PRIVATE LIMITED declares experience on 4 earlier projects. None of them carries a registration number we could match on MahaRERA, which is usual for work done before the register existed.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| VEDANT PEARL | 31 Dec 2011 | 25 Apr 2012 | +4 months |
| VEDANT SAPPHIRE | 31 Mar 2014 | 13 Nov 2013 | On time |
| VEDANT EMERALD I | 31 Aug 2014 | 16 Feb 2014 | On time |
| VEDANT DIAMOND | 31 Dec 2015 | 12 Mar 2015 | On time |
Frequently asked questions
How do I verify NANIS BUILDCON PRIVATE LIMITED as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with NANIS BUILDCON PRIVATE LIMITED?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.