Mohammed Salim Yusuf has 1 registration in this build, including Vrindavan Park. Its filings disclose 19 earlier MahaRERA projects: 18 of 19 past projects completed on time.

1Registrations in this build
19Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Vrindavan ParkThane, Maharashtra--Completed

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
classic apartment
19 Oct 199619 Oct 1996On time
choice apartment
8 Oct 19978 Oct 1997On time
lotus apartment
26 Oct 199726 Oct 1998+12 months
vrindavan apartment
25 Dec 199725 Dec 1997On time
kalpataru apartment
17 Jun 200020 May 2000On time
sai dham apartment
23 Mar 200123 Mar 2001On time
sai vihar apartment
17 Jun 200217 Jun 2002On time
Kalpaturu Residency
26 Sep 200526 Sep 2005On time
Vrindavan Residency Type A
25 Sep 200625 Sep 2006On time
Vrindavan Residency type B
11 Jul 200811 Jul 2008On time
Vrindavan Paradise A B and C
28 Apr 200928 Apr 2009On time
Vrindavan Valley
14 May 200914 May 2009On time

Frequently asked questions

How do I verify Mohammed Salim Yusuf as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Mohammed Salim Yusuf?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.