LEENA CONSTRUCTIONS has 2 registrations on MahaRERA, including Building A3 - VENICIA and AMIT APARTMENT. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time.
Projects by this developer
Showing all 2 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| Building A3 - VENICIAP52100046862 | Baner, Pune, 411045 | 72 | 40% | 14 Sep 2022 | Completed |
| AMIT APARTMENTPR1260002602345Redevelopment | KOTHRUD, Pune, 411038 | 29 | 0% | 16 Oct 2026 | Registered |
What this promoter declares as its own experience
LEENA CONSTRUCTIONS declares experience on 2 earlier projects. One carries a registration number we could match on MahaRERA, under this promoter's own name.
One of these declarations can be compared with the dates that project's own registration holds. On that one, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. That changes the arithmetic on the one completion recorded here as on time: measured against the original deadline the register itself holds, that one was finished after it.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Gururatna Heritage | 31 Dec 2020 | 31 Jul 2021 | +7 months |
| Building A3 - VENICIA P52100046862 | 30 Jun 2026 | 27 Apr 2026 | On time |
Frequently asked questions
How do I verify LEENA CONSTRUCTIONS as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27AAFFL1107Q1Z5 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with LEENA CONSTRUCTIONS?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.