Heritage Lifestyles and Developers Pvt. Ltd.: RERA track record

Company ยท attribution by exact filing name, entity resolution in progress

Heritage Lifestyles and Developers Pvt. Ltd. has 1 registration in this build, including Redevlopement of SBI Madhur Milan CHSL. Its filings disclose 8 earlier MahaRERA projects: 3 of 8 past projects completed on time.

1Registrations in this build
8Past projects disclosed
+6 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Redevlopement of SBI Madhur Milan CHSLMumbai Suburban, Maharashtra4420%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Krishna Heritage
31 Oct 201512 Oct 2015On time
Mahalaxmi Heritage
31 Dec 20152 Dec 2016+11 months
Heritage Castle
30 Sep 20168 Nov 2016+1 months
Redevlopment of TIRANDAZ SUBHA NIKETAN
31 Mar 201921 Dec 2021+33 months
ARUNODAY HERITAGE
31 May 20199 Dec 2020+18 months
APSARA HERITAGE
31 Dec 201925 Feb 2022+26 months
SUBHA HERITAGE
28 Feb 202121 Dec 2020On time
SANDHYA HERITAGE
30 Nov 20213 Aug 2021On time

Frequently asked questions

How do I verify Heritage Lifestyles and Developers Pvt. Ltd. as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Heritage Lifestyles and Developers Pvt. Ltd.?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.