GVC DEVELOPERS: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

GVC DEVELOPERS has 5 registrations on MahaRERA, including GVC GANGADHAM PHASE I and GVC SHAGUN PARK. Its filings disclose 7 earlier MahaRERA projects: declares 5 of 5 past projects completed on time.

5RERA registrations
7Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation
Follow this developer. An email when GVC DEVELOPERS registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 5 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
GVC GANGADHAM PHASE IP51100018353ASARJAN, Nanded, 431603750%24 Oct 2018Completed
GVC GANGADHAM SKYILAP51100055475ASARJAN, Nanded, 4316037138%2 Apr 2024Registered
GVC SAPTAGIRI SIGNATUREP51100051931KAUTHA, Nanded, 4316031292%13 Jul 2023Registered
GVC SAPTAGIRI GREENS IIP51100029308KAUTHA, Nanded, 431605--18 May 2021Completed
GVC SHAGUN PARKP51100026549NEAR MSRTC BUS STAND, Nanded, 431809--2 Oct 2020Registration lapsed

What this promoter declares as its own experience

GVC DEVELOPERS declares experience on 7 earlier projects. 5 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.

5 of these declarations can be compared with the dates those projects' own registrations hold. Every one of them gives the same original completion date its registration holds. A completion date is also recorded against 1 registration MahaRERA does not show as completed. A registration lapses when a promoter files neither a completion nor an extension, so that can mean the completion was never filed rather than that the project was not finished.

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
USHA RESIDENCY
30 Sep 20141 Jul 2014On time
RAMBAGH RESIDENCY
31 Dec 201731 Aug 2017On time
GVC GANGADHAM PHASE I
P51100018353
30 Mar 202214 Jan 2021On time
GVC SHAGUN PARK
P51100026549
30 Jun 202427 Jun 2023On time
GVC SAPTAGIRI GREENS II
P51100029308
31 Dec 202416 Apr 2024On time
GVC SAPTAGIRI SIGNATURE
P51100051931
31 Dec 2026Not completed yetOngoing
GVC GANGADHAM SKYILA
P51100055475
31 Dec 2028Not completed yetOngoing

Frequently asked questions

How do I verify GVC DEVELOPERS as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with GVC DEVELOPERS?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.

Report an error or share feedback

About the GVC DEVELOPERS developer page. Projects are grouped by the promoter name as filed, so a wrongly attributed project is the most useful thing to report.