ReraGenieLog inGet a buyer report

Home / Developers / AGNEL DEVELOPERS

AGNEL DEVELOPERS: RERA track record

Others ยท attribution by exact filing name, entity resolution in progress

AGNEL DEVELOPERS has 2 registrations in this build, including THE VIEWS and THE VIEWS II. Its filings disclose 12 earlier MahaRERA projects: 10 of 12 past projects completed on time. Litigation is declared on 2 of its registrations.

2Registrations in this build
12Past projects disclosed
on timeMedian delivery slip
2Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
THE VIEWSMumbai Suburban, Maharashtra28674%Registered
THE VIEWS IIMumbai Suburban, Maharashtra28646%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
SHOPPERS PLAZA
31 Mar 201731 Mar 2017On time
INSPIRE BKC PHASE 1 GROUND TO FORTH FLOOR
31 Dec 201716 Oct 2017On time
INSPIRE BKC PHASE 2 SIXTH AND SEVENTH FLOOR
31 Dec 201716 Oct 2017On time
Meadows G,H AND I
31 Dec 201731 Dec 2017On time
Meadows J AND K
31 Dec 201731 Dec 2017On time
WATERLILY PHASE 2
31 Dec 201731 Dec 2017On time
WATERLILY PHASE 3
31 Dec 201731 Dec 2017On time
WESTERN HEIGHTS PHASE 1 RESIDENTIAL
30 Jun 201815 Dec 2018+6 months
WESTERN HEIGHTS PHASE 2 COMMERCIAL 1ST AND 2ND FLOOR
30 Jun 201815 Dec 2018+6 months
Meadows A,B AND C
30 Jun 201830 Jun 2018On time
Meadows D,E AND F
30 Jun 201830 Jun 2018On time
WATERLILIY PHASE 4
30 Jun 201830 Jun 2018On time

Frequently asked questions

How do I verify AGNEL DEVELOPERS as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with AGNEL DEVELOPERS?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make AGNEL DEVELOPERS unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.