Home / Developers / ABHIJEET PRIDE
ABHIJEET PRIDE: RERA track record
GSTIN 27ABFFA9712M1Z3 · Partnership · attribution by exact filing name, entity resolution in progress
ABHIJEET PRIDE has 4 registrations on MahaRERA, including VISHWAJEET PRECIOUS PHASE I and VISHWAJEET PRECIOUS PHASE II. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time.
Projects by this developer
Showing all 4 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| VISHWAJEET PRECIOUS PHASE VPR1333032600324 | VARAP, Thane, 421301 | 98 | 0% | 4 May 2026 | Registered |
| VISHWAJEET PRECIOUS PHASE IP51700020587 | VARAP, Thane, 421301 | - | - | 26 Apr 2019 | Completed |
| VISHWAJEET PRECIOUS PHASE IIP51700030793 | TALUKA KALYAN, Thane, 421103 | - | - | 13 Sep 2021 | Completed |
| VISHWAJEET PRECIOUS PHASE IIIP51700031318 | VARAP, Thane, 421103 | - | - | 15 Oct 2021 | Completed |
What this promoter declares as its own experience
ABHIJEET PRIDE declares experience on 3 earlier projects. 3 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
3 of these declarations can be compared with the dates those projects' own registrations hold. Every one of them gives the same original completion date its registration holds.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| VISHWAJEET PRECIOUS PHASE III P51700031318 | 2 Mar 2024 | 29 Feb 2024 | On time |
| VISHWAJEET PRECIOUS PHASE I P51700020587 | 2 Mar 2025 | 9 Jun 2022 | On time |
| VISHWAJEET PRECIOUS PHASE II P51700030793 | 16 May 2026 | 29 Feb 2024 | On time |
Frequently asked questions
How do I verify ABHIJEET PRIDE as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27ABFFA9712M1Z3 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with ABHIJEET PRIDE?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.
Report an errorShare feedbackData from official MahaRERA filings. How we handle corrections is on the about page.