Valid until 30 Jun 2021 Residential/Group Housing project

VRAJ HARI

By J K CONSTRUCTON CO

RG-GJ-43200 · RERA PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/RAA05786/240719 · Last updated on GujRERA portal: 7 Nov 2019

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Jun 2021Possession promisedno revision filed
3 of 7Construction stages donefurthest along: Sanitary fittings within the flats, 90%
1 of 20Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

VRAJ HARI is a Residential/Group Housing project by J K CONSTRUCTON CO in Bhavnagar, Gujarat, registered with GujRERA as PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/RAA05786/240719 on 24 Jul 2019. Possession is promised by 30 Jun 2021. 19 of the 20 units on this registration are recorded sold or booked, and 3 of 7 construction stages are filed complete.

At a glance

Project

  • NameVRAJ HARI
  • TypeResidential/Group Housing
  • Location
    • PLOT NO. 9
    • HARIRAM BAUG
    • VADAVA
    • SURVEY NO. 253/2-2
    • NEAR GAURISHANKAR LAKE
    • BHAVNAGAR
    • Vadva
    • Bhavnagar
    • 364003
  • Pincode364003
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/RAA05786/240719
  • ReraGenie IDRG-GJ-43200

Builder

  • NameJ K CONSTRUCTON CO
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJul 2019PromisedJun 2021

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2021
  • Registered on24 Jul 2019
  • Promised completion30 Jun 2021
  • Revised completionNone
  • Buildings1 building record
  • Documents filed40 files

Current status

95%19 of 20 units booked
90.0%Of the estimated cost spent so far

Figures as on 7 Nov 2019, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---20020

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 7 Nov 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 7 construction stages are filed complete. The stage furthest along is Sanitary fittings within the flats, at 90%.

A: 94% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%

Progress on shared amenities19

As on 7 Nov 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsNoNot applicable
Water supplyYes90%
Sewerage (chamber, lines, septic tank, STP)Yes90%
Storm water drainsNoNot applicable
Landscaping and tree plantingNoNot applicable
Street lightingNoNot applicable
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes90%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes90%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area510 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 1.43 cr
Cost incurredRs 1.28 cr
Spent of the estimate90.0%
BuildingWingEstimatedIncurred
ANARs 1.43 crRs 1.28 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHEMAL BHATT
EngineerHITESH UNDAVIYA

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/RAA05786/240719 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)7 Nov 2019
Engineer's certificate (Form 2)7 Nov 2019
Engineer's certificate annexure7 Nov 2019
Accountant's certificate (Form 3)7 Nov 2019
RERA registration certificate24 Jul 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Bhavnagar

95%of this project is bookeddistrict median 50%
16%of Bhavnagar projects moved their completion datethis one has not

Computed across the 730+ Bhavnagar projects on ReraGenie, from their own filings.

Keep VRAJ HARI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadva730+ in Bhavnagar

2 kmVRAJ HARIOther 57Dot size: filed unitsN

Filed coordinates, straight-line distance. 57 registered projects within 2 km.

Builder: J K CONSTRUCTON CO

J K CONSTRUCTON CO has 1 registration on GujRERA, including VRAJ HARI. Read the full track record. See more projects on the Bhavnagar district page.

Frequently asked questions

What are my rights if VRAJ HARI is delayed beyond 30 Jun 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of VRAJ HARI?

The registered promoter entity is J K CONSTRUCTON CO, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in VRAJ HARI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at VRAJ HARI?

The professionals named in the filing: Architect: HEMAL BHATT; Engineer: HITESH UNDAVIYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VRAJ HARI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VRAJ HARI. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VRAJ HARI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.