ReraGenieLog inGet a buyer report

Home / Browse projects / Valsad, Gujarat / Vivan

Valid until 25 Jun 2027 Residential/Group Housing project

Vivan

By VIVAN ENTERPRISE

RG-GJ-56760 · RERA PR/GJ/VALSAD/PARDI/Others/RAA10021/EX1/130826/250627 · Last updated on GujRERA portal: 20 Jul 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Jun 2027Possession promisedmoved 12 months from the original
45 of 45Construction stages doneacross 5 buildings; every applicable stage filed complete
131 of 470Units unsoldnot recorded sold or booked
Jump to the 45 documents Report an error

Vivan is a Residential/Group Housing project by VIVAN ENTERPRISE in Valsad, Gujarat, registered with GujRERA as PR/GJ/VALSAD/PARDI/Others/RAA10021/EX1/130826/250627 on 13 Apr 2022. Possession is promised by 25 Jun 2027. The completion date has moved by 12 months from the original filing. 339 of the 470 units on this registration are recorded sold or booked, and 45 of 45 construction stages are filed complete.

At a glance

Project

  • NameVivan
  • TypeResidential/Group Housing
  • Location
    • Revenue Survey No. : 1647 (Old Survey No. 213/1/p4)
    • Vill. Chala
    • Vapi
    • Pardi
    • Valsad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VALSAD/PARDI/Others/RAA10021/EX1/130826/250627
  • ReraGenie IDRG-GJ-56760

Builder

  • NameVIVAN ENTERPRISE
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredApr 2022First promiseJun 2026Revised toJun 2027

Key facts

Registration and timeline

  • StatusValid until 25 Jun 2027
  • Registered on13 Apr 2022
  • Promised completion25 Jun 2027
  • Revised completionRevised to 25 Jun 2027 (originally 30 Jun 2026)
  • Buildings5 building records
  • Documents filed45 files

Current status

72%339 of 470 units booked
100.0%Of the estimated cost spent so far

Figures as on 20 Jul 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B1-B2---1040104
C1-C2---1040104
D---50050
E1-E2---1080108
A1-A2---1040104

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

45 of 45 construction stages are filed complete across 5 buildings.

B1-B2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C1-C2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E1-E2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A1-A2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,157 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 63.68 cr
Cost incurredRs 63.68 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
A1-A2NARs 14.68 crRs 14.68 cr
B1-B2NARs 14.61 crRs 14.61 cr
E1-E2NARs 14.40 crRs 14.40 cr
C1-C2NARs 13.49 crRs 13.49 cr
DNARs 6.49 crRs 6.49 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJenita Parikh
EngineerHemant A Shukla

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VALSAD/PARDI/Others/RAA10021/EX1/130826/250627Applied Jun 2026; approved Aug 2026

Documents filed45

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VALSAD/PARDI/Others/RAA10021/EX1/130826/250627 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)20 Jul 2026
Architect's certificate (Form 1)26 Jun 2026
Engineer's certificate (Form 2)26 Jun 2026
Engineer's certificate annexure26 Jun 2026
Site photograph, B1-B226 Jun 2026
Site photograph, C1-C226 Jun 2026
Site photograph, D26 Jun 2026
Site photograph, E1-E226 Jun 2026
Site photograph, A1-A226 Jun 2026
RERA registration certificate13 Apr 2022
Extension certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Valsad

72%of this project is bookeddistrict median 45%
23%of Valsad projects moved their completion datethis one moved by 12 months

Computed across the 390+ Valsad projects on ReraGenie, from their own filings.

Keep Vivan on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Valsad390+ in Valsad

2 kmVivanOther 84Dot size: filed unitsN

Filed coordinates, straight-line distance. 84 registered projects within 2 km.

Builder: VIVAN ENTERPRISE

VIVAN ENTERPRISE has 2 registrations on GujRERA, including Vivan and Silver Stone. Read the full track record. See more projects on the Valsad district page.

Frequently asked questions

What are my rights if Vivan is delayed beyond 25 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Vivan?

The registered promoter entity is VIVAN ENTERPRISE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Vivan?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Vivan?

The professionals named in the filing: Architect: Jenita Parikh; Engineer: Hemant A Shukla. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vivan?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vivan. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vivan to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.