Home / Browse projects / Ahmedabad, Gujarat / VERNIS VILLA

Valid until 31 Mar 2019 Residential/Group Housing project

VERNIS VILLA

By SAFAL GOYAL REALTY LLP

RG-GJ-08920 · RERA PR/GJ/AHMEDABAD/SANAND/AUDA/RAA00063/040917 · Last updated on GujRERA portal: 7 Jul 2018

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Mar 2019Possession promisedno revision filed
7 of 7Construction stages doneevery applicable stage filed complete
Jump to the 36 documents Report an error

VERNIS VILLA is a Residential/Group Housing project by SAFAL GOYAL REALTY LLP in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/SANAND/AUDA/RAA00063/040917 on 4 Sep 2017. Possession is promised by 31 Mar 2019.

At a glance

Project

  • NameVERNIS VILLA
  • TypeResidential/Group Housing
  • Location
    • O7 Club Road
    • Off S. P. Ring Road
    • Shela
    • Shela
    • Sanand
    • Ahmedabad
    • 380058
  • Pincode380058
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/SANAND/AUDA/RAA00063/040917
  • ReraGenie IDRG-GJ-08920

Builder

  • NameSAFAL GOYAL REALTY LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM
  • Other registrations15 more →

Key dates

this monthRegisteredSep 2017PromisedMar 2019

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2019
  • Registered on4 Sep 2017
  • Promised completion31 Mar 2019
  • Revised completionNone
  • Buildings1 building record
  • Documents filed36 files

Current status

101.3%Of the estimated cost spent so far

Figures as on 7 Jul 2018, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUNGALOWS-----73

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 7 Jul 2018, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 7 construction stages are filed complete.

BUNGALOWS: 100% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable

Progress on shared amenities19

As on 7 Jul 2018, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area44,360 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 48.43 cr
Cost incurredRs 49.05 cr
Spent of the estimate101.28%
BuildingWingEstimatedIncurred
BUNGALOWSNARs 48.43 crRs 49.05 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectApurv Amin
EngineerPrakashbhai (P Cube Consultants)

Documents filed36

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/SANAND/AUDA/RAA00063/040917 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)7 Jul 2018
Engineer's certificate (Form 2)7 Jul 2018
Site photograph, BUNGALOWS7 Jul 2018
RERA registration certificate4 Sep 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep VERNIS VILLA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Shela5,400+ in Ahmedabad

2 kmVERNIS VILLAOther 191Dot size: filed unitsN

Filed coordinates, straight-line distance. 191 registered projects within 2 km.

Builder: SAFAL GOYAL REALTY LLP

SAFAL GOYAL REALTY LLP has 16 registrations on GujRERA, including VERNIS VILLA and FLORIS VILLA. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if VERNIS VILLA is delayed beyond 31 Mar 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of VERNIS VILLA?

The registered promoter entity is SAFAL GOYAL REALTY LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in VERNIS VILLA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at VERNIS VILLA?

The professionals named in the filing: Architect: Apurv Amin; Engineer: Prakashbhai (P Cube Consultants). Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VERNIS VILLA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VERNIS VILLA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VERNIS VILLA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.