Home / Browse projects / Surat, Gujarat / Veer Arihanta

Valid until 30 Apr 2028 Mixed Development project

Veer Arihanta

By ARIHANTA INFRA

RG-GJ-57947 · RERA PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/MAA15230/170525/311227 · Last updated on GujRERA portal: 9 Mar 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2028Possession promisedno revision filed
10 of 28Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 95%
187 of 204Units unsoldnot recorded sold or booked
Jump to the 30 documents Report an error

Veer Arihanta is a Mixed Development project by ARIHANTA INFRA in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/MAA15230/170525/311227 on 17 May 2025. Possession is promised by 30 Apr 2028. 17 of the 204 units on this registration are recorded sold or booked, and 10 of 28 construction stages are filed complete.

At a glance

Project

  • NameVeer Arihanta
  • TypeMixed Development
  • Location
    • T.P.S.-No.14 (PAL)
    • F.P. No.96
    • Block No.360
    • Pal
    • Surat
    • Pal
    • Surat City
    • Surat
    • 395009
  • Pincode395009
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/MAA15230/170525/311227
  • ReraGenie IDRG-GJ-57947

Builder

  • NameARIHANTA INFRA
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMay 2025PromisedApr 2028

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2028
  • Registered on17 May 2025
  • Promised completion30 Apr 2028
  • Revised completionNone
  • Buildings3 building records
  • Documents filed30 files

Current status

8%17 of 204 units booked
25.2%Of the estimated cost spent so far

Figures as on 9 Mar 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A+B---9630126
D---52052
C---26026

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 9 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 28 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 95%.

A+B56%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure95%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
D49%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure85%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks35%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
C49%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure85%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks35%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 9 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes10%
Sewerage (chamber, lines, septic tank, STP)Yes10%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes10%
Electrical meter room, sub-station, receiving stationYes10%
Fire fightingYes25%
Drinking water facilitiesNoNot applicable
Emergency evacuationYes0%
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,558 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 73.00 cr
Cost incurredRs 18.39 cr
Spent of the estimate25.19%
BuildingWingEstimatedIncurred
A+BNARs 49.20 crRs 11.99 cr
DNARs 12.90 crRs 3.50 cr
CNARs 10.90 crRs 2.91 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANJAY RIDDHISHANKAR JOSHI
EngineerMAHESHKUMAR BHARATBHAI MALAVIYA

Documents filed30

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/MAA15230/170525/311227 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)9 Mar 2026
Engineer's certificate (Form 2)24 Feb 2026
Engineer's certificate annexure24 Feb 2026
Architect's certificate (Form 1)23 Feb 2026
Site photograph, A+B23 Feb 2026
Site photograph, D23 Feb 2026
Site photograph, C23 Feb 2026
RERA registration certificate17 May 2025
Proforma agreement for sale-
Project specific document-
Drainage affidavit-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Declaration in Form B1-
Declaration in Form B2-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Other document-
Project photograph-
Proforma sale deed-

How this compares with Surat

8%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one has not

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep Veer Arihanta on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Pal2,600+ in Surat

2 kmVeer ArihantaOther 173Dot size: filed unitsN

Filed coordinates, straight-line distance. 173 registered projects within 2 km.

Builder: ARIHANTA INFRA

ARIHANTA INFRA has 1 registration on GujRERA, including Veer Arihanta. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if Veer Arihanta is delayed beyond 30 Apr 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Veer Arihanta?

The registered promoter entity is ARIHANTA INFRA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Veer Arihanta?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Veer Arihanta?

The professionals named in the filing: Architect: SANJAY RIDDHISHANKAR JOSHI; Engineer: MAHESHKUMAR BHARATBHAI MALAVIYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Veer Arihanta?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Veer Arihanta. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Veer Arihanta to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.