ReraGenieLog inGet a buyer report

Home / Browse projects / Ahmedabad, Gujarat / UMANG ASLALI

Valid until 14 Oct 2027 Mixed Development project

UMANG ASLALI

By ANUBHUTI ENGINEERING PRIVATE LIMITED

RG-GJ-06243 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA02856/EX2/EX3/270826/141027 · Last updated on GujRERA portal: 6 Aug 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 94 months
  • 3 extensions taken

Clear

  • Separate project account declared
Oct 2027Possession promisedmoved 94 months from the original
23 of 36Construction stages doneacross 4 buildings; furthest along: External plumbing and external plaster, 95%
61 of 510Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

UMANG ASLALI is a Mixed Development project by ANUBHUTI ENGINEERING PRIVATE LIMITED in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA02856/EX2/EX3/270826/141027 on 7 Jun 2018. Possession is promised by 14 Oct 2027. The completion date has moved by 94 months from the original filing. 449 of the 510 units on this registration are recorded sold or booked, and 23 of 36 construction stages are filed complete.

At a glance

Project

  • NameUMANG ASLALI
  • TypeMixed Development
  • Location
    • umang aslali near saubhagiya hospital
    • aslali circle
    • aslali
    • Aslali
    • Ahmedabad City
    • Ahmedabad
    • 382427
  • Pincode382427
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA02856/EX2/EX3/270826/141027
  • ReraGenie IDRG-GJ-06243

Builder

  • NameANUBHUTI ENGINEERING PRIVATE LIMITED
  • Entity typeCOMPANY

Key dates

this monthRegisteredJun 2018First promiseDec 2019Revised toOct 2027

Key facts

Registration and timeline

  • StatusValid until 14 Oct 2027
  • Registered on7 Jun 2018
  • Promised completion14 Oct 2027
  • Revised completionRevised to 14 Oct 2027 (originally 15 Dec 2019)
  • Buildings4 building records
  • Documents filed43 files

Current status

88%449 of 510 units booked
95.2%Of the estimated cost spent so far

Figures as on 6 Aug 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block A+A1---1688176
Block B---9118109
Block C+D---1058113
Block E+F---1120112

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 6 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

23 of 36 construction stages are filed complete across 4 buildings. The stage furthest along is External plumbing and external plaster, at 95%.

Block A+A178%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats75%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing40%
Block B89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block C+D61%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flats40%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing35%
Block E+F89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 6 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes85%
Water supplyYes75%
Sewerage (chamber, lines, septic tank, STP)Yes60%
Storm water drainsYes75%
Landscaping and tree plantingYes50%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes60%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes60%
Electrical meter room, sub-station, receiving stationYes50%
Fire fightingYes50%
Drinking water facilitiesYes60%
Emergency evacuationNoNot applicable
Use of renewable energyYes50%
SecurityYes60%
Letter boxYes60%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,658 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 31.00 cr
Cost incurredRs 29.50 cr
Spent of the estimate95.16%
BuildingWingEstimatedIncurred
Block C+DNARs 8.00 crRs 7.00 cr
Block E+FNARs 8.00 crRs 8.00 cr
Block A+A1NARs 7.50 crRs 7.00 cr
Block BNARs 7.50 crRs 7.50 cr

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA02856/EX1/261219Applied Nov 2019; approved Dec 2019
PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA02856/EX2/200122Applied Jan 2022; approved Jan 2022
PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA02856/EX2/EX3/270826/141027Applied Nov 2023; approved Aug 2026

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA02856/EX2/EX3/270826/141027 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)6 Aug 2026
Architect's certificate (Form 1)19 May 2026
Engineer's certificate (Form 2)19 May 2026
Engineer's certificate annexure19 May 2026
Site photograph, Block A+A119 May 2026
Site photograph, Block A+A119 May 2026
Site photograph, Block B19 May 2026
Site photograph, Block C+D19 May 2026
Site photograph, Block E+F19 May 2026
Site photograph, Block E+F19 May 2026
RERA registration certificate7 Jun 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

88%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 94 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep UMANG ASLALI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Aslali5,400+ in Ahmedabad

2 kmUMANG ASLALIOther 108Dot size: filed unitsN

Filed coordinates, straight-line distance. 108 registered projects within 2 km.

Builder: ANUBHUTI ENGINEERING PRIVATE LIMITED

ANUBHUTI ENGINEERING PRIVATE LIMITED has 1 registration on GujRERA, including UMANG ASLALI. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if UMANG ASLALI is delayed beyond 14 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of UMANG ASLALI?

The registered promoter entity is ANUBHUTI ENGINEERING PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in UMANG ASLALI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in UMANG ASLALI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About UMANG ASLALI. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save UMANG ASLALI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.