ReraGenieLog inGet a buyer report

Home / Browse projects / Rajkot, Gujarat / TORAL APARTMENT

Valid until 30 Sep 2021 Residential/Group Housing project

TORAL APARTMENT

By RAMDUT BUILDERS AND DEVELOPERS

RG-GJ-99210 · RERA PR/GJ/RAJKOT/RAJKOT/Others/RAA05031/EX1/091020 · Last updated on GujRERA portal: 29 Sep 2021

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Sep 2021Possession promisedmoved 12 months from the original
9 of 9Construction stages doneevery applicable stage filed complete
32 of 32Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

TORAL APARTMENT is a Residential/Group Housing project by RAMDUT BUILDERS AND DEVELOPERS in Rajkot, Gujarat, registered with GujRERA as PR/GJ/RAJKOT/RAJKOT/Others/RAA05031/EX1/091020 on 12 Mar 2019. Possession is promised by 30 Sep 2021. The completion date has moved by 12 months from the original filing. 0 of the 32 units on this registration are recorded sold or booked, and 9 of 9 construction stages are filed complete.

At a glance

Project

  • NameTORAL APARTMENT
  • TypeResidential/Group Housing
  • Location
    • TORAL APARTMENT
    • ANGEL PARK
    • BH SWAMINARAYAN GURUKUL
    • OPP SHIVAM PARK
    • NR KHODIYAR CHOWK
    • MAVDI
    • Mavdi
    • Rajkot
    • 360004
  • Pincode360004
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/RAJKOT/RAJKOT/Others/RAA05031/EX1/091020
  • ReraGenie IDRG-GJ-99210

Builder

  • NameRAMDUT BUILDERS AND DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMar 2019First promiseSep 2020Revised toSep 2021

Key facts

Registration and timeline

  • StatusValid until 30 Sep 2021
  • Registered on12 Mar 2019
  • Promised completion30 Sep 2021
  • Revised completionRevised to 30 Sep 2021 (originally 30 Sep 2020)
  • Buildings1 building record
  • Documents filed41 files

Current status

0%0 of 32 units booked
100.0%Of the estimated cost spent so far

Figures as on 29 Sep 2021, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1---32032

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 29 Sep 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 9 construction stages are filed complete.

1: 100% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 29 Sep 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsNoNot applicable
Water supplyNoNot applicable
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingNoNot applicable
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area987 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 3.96 cr
Cost incurredRs 3.96 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
1NARs 3.96 crRs 3.96 cr

Certifying professionals and partners1

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJAWAHAR MORI

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/RAJKOT/RAJKOT/Others/RAA05031/EX1/091020Applied Sep 2020; approved Oct 2020

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/RAJKOT/RAJKOT/Others/RAA05031/EX1/091020 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)29 Sep 2021
Engineer's certificate (Form 2)29 Sep 2021
Engineer's certificate annexure29 Sep 2021
Accountant's certificate (Form 3)29 Sep 2021
Site photograph, 129 Sep 2021
RERA registration certificate12 Mar 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Rajkot

0%of this project is bookeddistrict median 56%
13%of Rajkot projects moved their completion datethis one moved by 12 months

Computed across the 1,800+ Rajkot projects on ReraGenie, from their own filings.

Keep TORAL APARTMENT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Mavdi1,800+ in Rajkot

2 kmTORAL APARTMENTOther 381Dot size: filed unitsN

Filed coordinates, straight-line distance. 381 registered projects within 2 km.

Builder: RAMDUT BUILDERS AND DEVELOPERS

RAMDUT BUILDERS AND DEVELOPERS has 1 registration on GujRERA, including TORAL APARTMENT. Read the full track record. See more projects on the Rajkot district page.

Frequently asked questions

What are my rights if TORAL APARTMENT is delayed beyond 30 Sep 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of TORAL APARTMENT?

The registered promoter entity is RAMDUT BUILDERS AND DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in TORAL APARTMENT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at TORAL APARTMENT?

The professionals named in the filing: Architect: JAWAHAR MORI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TORAL APARTMENT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TORAL APARTMENT. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TORAL APARTMENT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.