ReraGenieLog inGet a buyer report

Home / Browse projects / Patan, Gujarat / TIRUPATI RESIDENCY

Valid until 30 Apr 2028 Residential/Group Housing project

TIRUPATI RESIDENCY

By TIRUPATI DEVELOPERS

RG-GJ-55695 · RERA PR/GJ/PATAN/PATAN/Patan Area Development Authority/RAA16278/010126/311227 · Last updated on GujRERA portal: 1 Jan 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2028Possession promisedno revision filed
2 of 18Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 60%
35 of 35Units unsoldnot recorded sold or booked
Jump to the 37 documents Report an error

TIRUPATI RESIDENCY is a Residential/Group Housing project by TIRUPATI DEVELOPERS in Patan, Gujarat, registered with GujRERA as PR/GJ/PATAN/PATAN/Patan Area Development Authority/RAA16278/010126/311227 on 1 Jan 2026. Possession is promised by 30 Apr 2028. 0 of the 35 units on this registration are recorded sold or booked, and 2 of 18 construction stages are filed complete.

At a glance

Project

  • NameTIRUPATI RESIDENCY
  • TypeResidential/Group Housing
  • Location
    • TIRUPATI RESIDENCY
    • NR. BALAJI GREEN
    • NIRMAL NAGAR ROAD
    • GUNGADIPATI
    • Patan
    • 384265
  • Pincode384265
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/PATAN/PATAN/Patan Area Development Authority/RAA16278/010126/311227
  • ReraGenie IDRG-GJ-55695

Builder

  • NameTIRUPATI DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations7 more →

Key dates

this monthRegisteredJan 2026PromisedApr 2028

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2028
  • Registered on1 Jan 2026
  • Promised completion30 Apr 2028
  • Revised completionNone
  • Buildings2 building records
  • Documents filed37 files

Current status

0%0 of 35 units booked
39.0%Of the estimated cost spent so far

Figures as on 1 Jan 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TYPE A TO A3(BUNGLOW 1 TO 34)---34034
TYPE A3(BUNGLOW 35)---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 1 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 60%.

TYPE A TO A3(BUNGLOW 1 TO 34)24%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure60%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing10%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE A3(BUNGLOW 35)24%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure60%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing10%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 1 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes20%
Sewerage (chamber, lines, septic tank, STP)Yes10%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,897 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 4.00 cr
Cost incurredRs 1.56 cr
Spent of the estimate39.0%
BuildingWingEstimatedIncurred
TYPE A TO A3(BUNGLOW 1 TO 34)NARs 3.80 crRs 1.50 cr
TYPE A3(BUNGLOW 35)NARs 20.00 lakhRs 6.00 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUrvashi Lalitkumar Tuli
EngineerMEET RAJESHKUMAR PATEL

Documents filed37

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/PATAN/PATAN/Patan Area Development Authority/RAA16278/010126/311227 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RERA registration certificate1 Jan 2026
Architect's certificate (Form 1)26 Nov 2025
Engineer's certificate (Form 2)26 Nov 2025
Engineer's certificate annexure26 Nov 2025
Accountant's certificate (Form 3)26 Nov 2025
Site photograph, TYPE A TO A3(BUNGLOW 1 TO 34)26 Nov 2025
Site photograph, TYPE A TO A3(BUNGLOW 1 TO 34)26 Nov 2025
Site photograph, TYPE A TO A3(BUNGLOW 1 TO 34)26 Nov 2025
Site photograph, TYPE A TO A3(BUNGLOW 1 TO 34)26 Nov 2025
Site photograph, TYPE A TO A3(BUNGLOW 1 TO 34)26 Nov 2025
Site photograph, TYPE A TO A3(BUNGLOW 1 TO 34)26 Nov 2025
Site photograph, TYPE A3(BUNGLOW 35)26 Nov 2025
Proforma agreement for sale-
Auditor's report (3 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (3 of 3)-

How this compares with Patan

0%of this project is bookeddistrict median 35%
16%of Patan projects moved their completion datethis one has not

Computed across the 49 Patan projects on ReraGenie, from their own filings.

Keep TIRUPATI RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near GUNGADIPATI49 in Patan

2 kmTIRUPATI RESIDENCYOther 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 23 registered projects within 2 km.

Builder: TIRUPATI DEVELOPERS

Tirupati Developers has 8 registrations on GujRERA, including SOLITAIRE RESIDE and SHIVALAY ARCADE. Read the full track record. See more projects on the Patan district page.

Frequently asked questions

What are my rights if TIRUPATI RESIDENCY is delayed beyond 30 Apr 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of TIRUPATI RESIDENCY?

The registered promoter entity is TIRUPATI DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in TIRUPATI RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at TIRUPATI RESIDENCY?

The professionals named in the filing: Architect: Urvashi Lalitkumar Tuli; Engineer: MEET RAJESHKUMAR PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TIRUPATI RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TIRUPATI RESIDENCY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TIRUPATI RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.