Home / Browse projects / Gir Somnath, Gujarat / TIRTHRAJ RESIDENCY
TIRTHRAJ RESIDENCY
RG-GJ-52409 · RERA PR/GJ/GIR SOMNATH/VERAVAL/Veraval-Patan Municipality/MAA15316/090625/311228 · Last updated on GujRERA portal: 9 Jun 2025
Source: official GujRERA filing
Red flags
- No red flags in this filing
Clear
- Completion date never moved
Saved.
TIRTHRAJ RESIDENCY is a Mixed Development project by TIRTHRAJ DEVELOPERS in Gir Somnath, Gujarat, registered with GujRERA as PR/GJ/GIR SOMNATH/VERAVAL/Veraval-Patan Municipality/MAA15316/090625/311228 on 9 Jun 2025. Possession is promised by 30 Apr 2029. 0 of the 44 units on this registration are recorded sold or booked, and 2 of 9 construction stages are filed complete.
At a glance
Project
- NameTIRTHRAJ RESIDENCY
- TypeMixed Development
- Location
- Community Hall Road
- Near Kapishwar Party Plot
- Veraval
- Veraval
- Gir Somnath
- 362265
- Pincode362265
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/GIR SOMNATH/VERAVAL/Veraval-Patan Municipality/MAA15316/090625/311228
- ReraGenie IDRG-GJ-52409
Builder
- NameTIRTHRAJ DEVELOPERS
- Entity typePARTNERSHIP FIRM
Key dates
Key facts
Registration and timeline
- StatusValid until 30 Apr 2029
- Registered on9 Jun 2025
- Promised completion30 Apr 2029
- Revised completionNone
- Buildings1 building record
- Documents filed37 files
Current status
Figures as on 9 Jun 2025, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | - | - | - | 28 | 16 | 44 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building1
As on 9 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 9 construction stages are filed complete. The stage furthest along is Stilt Floor, at 10%.
A: 23% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 10% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
Progress on shared amenities19
As on 9 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 0% |
| Water supply | Yes | 0% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 0% |
| Storm water drains | Yes | 0% |
| Landscaping and tree planting | Yes | 0% |
| Street lighting | Yes | 0% |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | Yes | 0% |
| Solid waste management and disposal | Yes | 0% |
| Water conservation, rain water harvesting | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Fire fighting | Yes | 0% |
| Drinking water facilities | Yes | 0% |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 0% |
| Letter box | Yes | 0% |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A | NA | Rs 7.64 cr | Rs 1.50 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MAITRI UPENDRA MODI |
| Engineer | ASHWINKUMAR MANILAL LODHIYA |
Documents filed37
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GIR SOMNATH/VERAVAL/Veraval-Patan Municipality/MAA15316/090625/311228 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| RERA registration certificate | 9 Jun 2025 |
| Accountant's certificate (Form 3) | 13 May 2025 |
| Architect's certificate (Form 1) | 1 Feb 2025 |
| Engineer's certificate (Form 2) | 1 Feb 2025 |
| Engineer's certificate annexure | 1 Feb 2025 |
| Site photograph, A | 1 Feb 2025 |
| Proforma agreement for sale | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Drainage affidavit | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Declaration in Form B | - |
| Approved building or plotting plan | - |
| NOCs from authorities | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Statutory document | - |
| Project photograph | - |
| Proforma sale deed | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Gir Somnath
Computed across the 20 Gir Somnath projects on ReraGenie, from their own filings.
Keep TIRTHRAJ RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Veraval20 in Gir Somnath
Filed coordinates, straight-line distance. 11 registered projects within 2 km.
SAI GOLD
SUNILKUMARKISHANCHANDMOHNANI & Others
DAMODAR PRIDE
AARNA CONSTRUCTION CO
ADITYA HEIGHTS
VIVEKBHAIVIJAYBHAIHINDOCHA AND OTHERS
RUDRAX SQUARE
Rise Developers
AKSHAR ARCADE
Akshar Developers
VINAYAK APARTMENTS
VINAYAK DEVELOPERS
See every Gir Somnath project, with the district possession charts
Builder: TIRTHRAJ DEVELOPERS
TIRTHRAJ DEVELOPERS has 1 registration on GujRERA, including TIRTHRAJ RESIDENCY. Read the full track record. See more projects on the Gir Somnath district page.
Frequently asked questions
What are my rights if TIRTHRAJ RESIDENCY is delayed beyond 30 Apr 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of TIRTHRAJ RESIDENCY?
The registered promoter entity is TIRTHRAJ DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in TIRTHRAJ RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at TIRTHRAJ RESIDENCY?
The professionals named in the filing: Architect: MAITRI UPENDRA MODI; Engineer: ASHWINKUMAR MANILAL LODHIYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in TIRTHRAJ RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.
Report an error Share feedback