Valid until 25 Oct 2026 Commercial project

Times Square Grand

By SHREENATHJI INFRA SPACE LLP

RG-GJ-15042 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/CAA05982/A1C/EX2/181025/251026 · Last updated on GujRERA portal: 10 Oct 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Oct 2026Possession promisedmoved 24 months from the original
8 of 9Construction stages donefurthest along: Stilt Floor, 0%
6 of 110Units unsoldnot recorded sold or booked
Jump to the 44 documents Report an error

Times Square Grand is a Commercial project by SHREENATHJI INFRA SPACE LLP in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/CAA05982/A1C/EX2/181025/251026 on 30 Aug 2019. Possession is promised by 25 Oct 2026. The completion date has moved by 24 months from the original filing. 104 of the 110 units on this registration are recorded sold or booked, and 8 of 9 construction stages are filed complete.

At a glance

Project

  • NameTimes Square Grand
  • TypeCommercial
  • Location
    • Times Square Grand
    • Plot No. 53
    • Nr. Sindhu Bhavan
    • Opp. Goga Maharaj Mandir
    • Sindhu Bhavan Road
    • Thaltej
    • Ahmedabad - 380059
    • Thaltej
    • Ahmedabad City
    • ...
  • Pincode380054
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/CAA05982/A1C/EX2/181025/251026
  • ReraGenie IDRG-GJ-15042

Builder

  • NameSHREENATHJI INFRA SPACE LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM

Key dates

this monthRegisteredAug 2019First promiseOct 2024Revised toOct 2026

Key facts

Registration and timeline

  • StatusValid until 25 Oct 2026
  • Registered on30 Aug 2019
  • Promised completion25 Oct 2026
  • Revised completionRevised to 25 Oct 2026 (originally 30 Oct 2024)
  • Buildings1 building record
  • Documents filed44 files

Current status

95%104 of 110 units booked
98.6%Of the estimated cost spent so far

Figures as on 10 Oct 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---0109110

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 10 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 9 construction stages are filed complete. The stage furthest along is Stilt Floor, at 0%.

A: 89% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 10 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationYes100%
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,362 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 91.00 cr
Cost incurredRs 89.70 cr
Spent of the estimate98.57%
BuildingWingEstimatedIncurred
ANARs 91.00 crRs 89.70 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVISHESH JIGNESH PATEL
EngineerVIJAYKUMAR DASHRATHLAL SHAH

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA05982/EX1/100125/251025Applied Sep 2024; approved Jan 2025
PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/CAA05982/A1C/EX2/181025/251026Applied Sep 2025; approved Oct 2025

Documents filed44

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/CAA05982/A1C/EX2/181025/251026 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)10 Oct 2025
Architect's certificate (Form 1)22 Sep 2025
Engineer's certificate (Form 2)22 Sep 2025
Engineer's certificate annexure22 Sep 2025
Site photograph, A22 Sep 2025
RERA registration certificate30 Aug 2019
Extension certificate-
Alteration certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Approved building or plotting plan-
Title clearance certificate-
Title report-
Property card-
Proforma sale deed-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

95%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 24 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep Times Square Grand on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Thaltej5,400+ in Ahmedabad

2 kmTimes Square GrandOther 190Dot size: filed unitsN

Filed coordinates, straight-line distance. 190 registered projects within 2 km.

Builder: SHREENATHJI INFRA SPACE LLP

SHREENATHJI INFRA SPACE LLP has 1 registration on GujRERA, including Times Square Grand. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if Times Square Grand is delayed beyond 25 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Times Square Grand?

The registered promoter entity is SHREENATHJI INFRA SPACE LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Times Square Grand?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Times Square Grand?

The professionals named in the filing: Architect: VISHESH JIGNESH PATEL; Engineer: VIJAYKUMAR DASHRATHLAL SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Times Square Grand?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Times Square Grand. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Times Square Grand to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.