Home / Browse projects / Koppal, Karnataka / TILAKABHIRAMARAO
TILAKABHIRAMARAO
RG-KA-21132 · RERA PRM/KA/RERA/1266/390/PR/191222/005530 · Last updated on RERA Karnataka portal: 2 Dec 2022
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
TILAKABHIRAMARAO is a Plotted Development project by TILAKABHIRAMARAO in Koppal, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1266/390/PR/191222/005530 on 19 Dec 2022. Possession is promised by 1 Feb 2023.
At a glance
Project
- NameTILAKABHIRAMARAO
- TypePlotted Development
- Location
- Koppal
- PincodeNot stated
- RERA no.PRM/KA/RERA/1266/390/PR/191222/005530
- ReraGenie IDRG-KA-21132
Builder
- NameTILAKABHIRAMARAO
- Entity typeProprietorship Firm
- Authorized SignatoryTILAKABHIRAMARAO
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on19 Dec 2022
- Promised completion1 Feb 2023
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed131 files
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| TILAKABHIRAMRAO PADAKI | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 54.52 lakh | - |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Engineer | PAVAN KUMAR PATIL |
| Chartered Accountant | H R KOPPAR |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed131
As listed on the registration, under the names the promoter filed them with; the newest 80 of 131 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1266/390/PR/191222/005530 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CA CERTIFICATE FORM 1File: Ca Ceriticate Form 1new.pdf | 2 Dec 2022 |
| ASSETS AND LIABILITIESFile: TILAK PADAKI networth.pdf | 2 Dec 2022 |
| affidavit 3(1)File: affidavit 3(1).pdf | 19 Nov 2022 |
| Agreement For SaleFile: Agreement For Sale.pdf | 19 Nov 2022 |
| brief estimateFile: brief estimate.pdf | 19 Nov 2022 |
| CA Certificate Form_1File: CA Certificate Form_1.pdf | 19 Nov 2022 |
| CA CertificateFile: CA Certificate.pdf | 19 Nov 2022 |
| Engineeer Certificate Form_3File: Engineeer Certificate Form_3.pdf | 19 Nov 2022 |
| Form_BFile: Form_B.pdf | 19 Nov 2022 |
| Power Supply NOCFile: Power Supply NOC.pdf | 19 Nov 2022 |
| Septic Tank DemarcationFile: Septic Tank Demarcation.pdf | 19 Nov 2022 |
| SOLD AND UNSOLD declarationFile: SOLD AND UNSOLD declaration.pdf | 19 Nov 2022 |
| PROJECT SPECIFICATIONFile: PROJECT SPECIFICATION.pdf | 19 Nov 2022 |
| ATTCHMENT 1File: 1.pdf | 31 Oct 2022 |
| ATT 2File: 2.pdf | 31 Oct 2022 |
| ATTA 3File: 3.pdf | 31 Oct 2022 |
| ATT 4File: 4.pdf | 31 Oct 2022 |
| ATT 5File: 5.pdf | 31 Oct 2022 |
| ATT 6File: 6 new.pdf | 31 Oct 2022 |
| ATT 7File: 7.pdf | 31 Oct 2022 |
| ATT 8File: 8.pdf | 31 Oct 2022 |
| ATT 9File: 9 new.pdf | 31 Oct 2022 |
| ATT 10File: 10.pdf | 31 Oct 2022 |
| ATT 11File: 11.pdf | 31 Oct 2022 |
| ATT 12File: 12.pdf | 31 Oct 2022 |
| ATT 13File: 13 new.pdf | 31 Oct 2022 |
| ATT 14File: 14.pdf | 31 Oct 2022 |
| ATT 15File: 15.pdf | 31 Oct 2022 |
| ATT 16File: 16.pdf | 31 Oct 2022 |
| ATT 17File: 17 new.pdf | 31 Oct 2022 |
| ATT 18File: AFFIDAVIT.pdf | 31 Oct 2022 |
| ATT 19File: CDP MAP showing proposed site.pdf | 31 Oct 2022 |
| ATT 20File: certified copy from subregistrar regarding valur of property on guidance value.pdf | 31 Oct 2022 |
| ATT 21File: Development details with engineer registration and licence.pdf | 31 Oct 2022 |
| ATT 22File: layout approval by kuda colour.pdf | 31 Oct 2022 |
| ATT 23File: layout map colour.pdf | 31 Oct 2022 |
| ATT 24File: non litigation notary.pdf | 31 Oct 2022 |
| ATT 25File: village demarcation drawing.pdf | 31 Oct 2022 |
| ATT 26File: water dept complition letter.pdf | 31 Oct 2022 |
| RTC, survey 92/5 | - |
| Mutation, survey 92/5 | - |
| Encumbrance Certificate, survey 92/5 | - |
| Conversion/Alienation Order, survey 92/5 | - |
| Khatha, survey 92/5 | - |
| Registration CertificateFile: pan.jpeg | - |
| Certificate issued by CA Form 1File: CA Certificate Form_1.pdf | - |
| Certificate issued by Engineer Form 3File: Engineeer Certificate Form_3.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| AffidavitFile: affidavit (1) signed_NEW.pdf | - |
| Certificate from Chartered AccountFile: Form1_NEW.pdf | - |
| Certificate issued by ArchitectFile: IMG_20220606_0004.pdf | - |
| Balance Sheet 2020 - 2021File: CA site handover and EC_NEW.pdf | - |
| Balance Sheet 2019 - 2020File: CA site handover and EC_NEW.pdf | - |
| Balance Sheet 2018 - 2019File: CA site handover and EC_NEW.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: CA site handover and EC_NEW.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: CA site handover and EC_NEW.pdf | - |
| Audited Profit and Loss Statement 2018 - 2019File: CA site handover and EC_NEW.pdf | - |
| Director's Report 2020 - 2021File: CA site handover and EC_NEW.pdf | - |
| Director's Report 2019 - 2020File: CA site handover and EC_NEW.pdf | - |
| Director's Report 2018 - 2019File: CA site handover and EC_NEW.pdf | - |
| Cash Flow Statement 2020 - 2021File: CA site handover and EC_NEW.pdf | - |
| Cash Flow Statement 2019 - 2020File: CA site handover and EC_NEW.pdf | - |
| Auditor's Report 2020 - 2021File: CA site handover and EC_NEW.pdf | - |
| Auditor's Report 2019 - 2020File: CA site handover and EC_NEW.pdf | - |
| Auditor's Report 2018 - 2019File: CA site handover and EC_NEW.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: CA site handover and EC_NEW.pdf | - |
| Income Tax Return Acknowledgement 2019 - 2020File: CA site handover and EC_NEW.pdf | - |
| Income Tax Return Acknowledgement 2018 - 2019File: CA site handover and EC_NEW.pdf | - |
| IMG_20220606_0001 | - |
| KPTCL NEW | - |
| IMG_20220606_0003 | - |
| IMG_20220606_0001 | - |
| CA site handover and EC | - |
| CA site handover and EC_NEW | - |
| CA site handover and EC_NEW | - |
| IMG_20220606_0001 | - |
| IMG_20220606_0001 | - |
| IMG_20220606_0005 NEW | - |
| IMG_20220606_0003 | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Koppal
Computed across the 48 Koppal projects on ReraGenie, from their own filings.
Keep TILAKABHIRAMARAO on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Koppal48 in Koppal
Aasti developers colony
Mohsin Jamal
BOMMANAL ENCLAVE
Gavi Constructions
Balakrishna Badavane
Vijaykumar S Jahagirdar
Bhoomraddi Developer
SURESH SHIVARUDRAPPA BHOOMRADDI
CONSTRUCTION OF 200 HOUSES AT GANGAVATI TOWN
Karnataka
CONSTRUCTION OF 402 HOUSES AT KOPPAL
Karnataka Slum Development Board
See every Koppal project, with the district possession charts
Builder: TILAKABHIRAMARAO
TILAKABHIRAMARAO has 1 registration on RERA Karnataka, including TILAKABHIRAMARAO. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Koppal district page.
Frequently asked questions
What are my rights if TILAKABHIRAMARAO is delayed beyond 1 Feb 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of TILAKABHIRAMARAO?
The registered promoter entity is TILAKABHIRAMARAO, a proprietorship firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in TILAKABHIRAMARAO?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at TILAKABHIRAMARAO?
The professionals named in the filing: Engineer: PAVAN KUMAR PATIL; Chartered Accountant: H R KOPPAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in TILAKABHIRAMARAO?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback