ReraGenieLog inGet a buyer report

Home / Browse projects / Rajkot, Gujarat / THE GREEN MOON

Valid until 31 Dec 2024 Residential/Group Housing project

THE GREEN MOON

By PATIDAR INFRA

RG-GJ-97234 · RERA PR/GJ/RAJKOT/RAJKOT/Others/RAA07317/140820 · Last updated on GujRERA portal: 28 Dec 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Dec 2024Possession promisedno revision filed
18 of 18Construction stages doneacross 2 buildings; every applicable stage filed complete
12 of 52Units unsoldnot recorded sold or booked
Jump to the 42 documents Report an error

THE GREEN MOON is a Residential/Group Housing project by PATIDAR INFRA in Rajkot, Gujarat, registered with GujRERA as PR/GJ/RAJKOT/RAJKOT/Others/RAA07317/140820 on 14 Aug 2020. Possession is promised by 31 Dec 2024. 40 of the 52 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.

At a glance

Project

  • NameTHE GREEN MOON
  • TypeResidential/Group Housing
  • Location
    • Survey no. 131P1/P2
    • F.P.No. 18/2
    • Motamava
    • Rajkot
    • Motamava
    • Rajkot
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/RAJKOT/RAJKOT/Others/RAA07317/140820
  • ReraGenie IDRG-GJ-97234

Builder

  • NamePATIDAR INFRA
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredAug 2020PromisedDec 2024

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2024
  • Registered on14 Aug 2020
  • Promised completion31 Dec 2024
  • Revised completionNone
  • Buildings2 building records
  • Documents filed42 files

Current status

77%40 of 52 units booked
100.0%Of the estimated cost spent so far

Figures as on 28 Dec 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER-A---26026
TOWER-B---26026

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 28 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete across 2 buildings.

TOWER-A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER-B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 28 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsNoNot applicable
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingNoNot applicable
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyYes100%
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,073 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 11.80 cr
Cost incurredRs 11.80 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
TOWER-ANARs 5.90 crRs 5.90 cr
TOWER-BNARs 5.90 crRs 5.90 cr

Certifying professionals and partners1

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNIMESH A. ASHAR

Documents filed42

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/RAJKOT/RAJKOT/Others/RAA07317/140820 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)28 Dec 2024
Engineer's certificate (Form 2)28 Dec 2024
Engineer's certificate annexure28 Dec 2024
Accountant's certificate (Form 3)28 Dec 2024
Site photograph, TOWER-A28 Dec 2024
Site photograph, TOWER-B28 Dec 2024
RERA registration certificate14 Aug 2020
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Rajkot

77%of this project is bookeddistrict median 56%
13%of Rajkot projects moved their completion datethis one has not

Computed across the 1,800+ Rajkot projects on ReraGenie, from their own filings.

Keep THE GREEN MOON on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Motamava1,800+ in Rajkot

2 kmTHE GREEN MOONOther 198Dot size: filed unitsN

Filed coordinates, straight-line distance. 198 registered projects within 2 km.

Builder: PATIDAR INFRA

PATIDAR INFRA has 1 registration on GujRERA, including THE GREEN MOON. Read the full track record. See more projects on the Rajkot district page.

Frequently asked questions

What are my rights if THE GREEN MOON is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of THE GREEN MOON?

The registered promoter entity is PATIDAR INFRA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in THE GREEN MOON?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at THE GREEN MOON?

The professionals named in the filing: Architect: NIMESH A. ASHAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE GREEN MOON?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE GREEN MOON. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE GREEN MOON to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.