ReraGenieLog inGet a buyer report

Home / Browse projects / Valsad, Gujarat / THE CENTRAL HOME & RETAILS

Valid until 29 Sep 2026 Mixed Development project

THE CENTRAL HOME & RETAILS

By PARAM INFRA SPACE Partnership Firm

RG-GJ-51265 · RERA PR/GJ/VALSAD/PARDI/Others/MAA05412/EX1/EX3/290526/290926 · Last updated on GujRERA portal: 20 May 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 36 months
  • 3 extensions taken

Clear

  • Nothing verified clear yet
Sep 2026Possession promisedmoved 36 months from the original
33 of 36Construction stages doneacross 4 buildings; furthest along: External plumbing and external plaster, 95%
146 of 288Units unsoldnot recorded sold or booked
Jump to the 45 documents Report an error

THE CENTRAL HOME & RETAILS is a Mixed Development project by PARAM INFRA SPACE Partnership Firm in Valsad, Gujarat, registered with GujRERA as PR/GJ/VALSAD/PARDI/Others/MAA05412/EX1/EX3/290526/290926 on 10 May 2019. Possession is promised by 29 Sep 2026. The completion date has moved by 36 months from the original filing. 142 of the 288 units on this registration are recorded sold or booked, and 33 of 36 construction stages are filed complete.

At a glance

Project

  • NameTHE CENTRAL HOME & RETAILS
  • TypeMixed Development
  • Location
    • CITY SURVEY NO 1437/1
    • 1492
    • 1570
    • BEHIND VEGETABLE MARKET
    • VAPI TOWN
    • VAPI
    • Vapi
    • Pardi
    • Valsad
    • 396191
  • Pincode396191
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VALSAD/PARDI/Others/MAA05412/EX1/EX3/290526/290926
  • ReraGenie IDRG-GJ-51265

Builder

  • NamePARAM INFRA SPACE Partnership Firm
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMay 2019First promiseSep 2023Revised toSep 2026

Key facts

Registration and timeline

  • StatusValid until 29 Sep 2026
  • Registered on10 May 2019
  • Promised completion29 Sep 2026
  • Revised completionRevised to 29 Sep 2026 (originally 30 Sep 2023)
  • Buildings4 building records
  • Documents filed45 files

Current status

49%142 of 288 units booked
97.2%Of the estimated cost spent so far

Figures as on 20 May 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING A---4852100
WING B---6076136
WING C---122436
WING D---01616

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 20 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

33 of 36 construction stages are filed complete across 4 buildings. The stage furthest along is External plumbing and external plaster, at 95%.

WING A98%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%
WING B99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
WING C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
WING D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 20 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes70%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)NoNot applicable
Storm water drainsNoNot applicable
Landscaping and tree plantingNoNot applicable
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes80%
Solid waste management and disposalYes80%
Water conservation, rain water harvestingYes80%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes80%
Fire fightingYes80%
Drinking water facilitiesYes80%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,894 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 21.75 cr
Cost incurredRs 21.15 cr
Spent of the estimate97.22%
BuildingWingEstimatedIncurred
WING BNARs 9.29 crRs 9.29 cr
WING ANARs 7.23 crRs 6.62 cr
WING CNARs 3.83 crRs 3.83 cr
WING DNARs 1.40 crRs 1.40 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDEVDATT MAYUR PANDYA
EngineerJAYKUMAR ASSUDANI

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VALSAD/PARDI/Others/MAA05412/EX1/260424/290924Applied Oct 2023; approved Apr 2024
PR/GJ/VALSAD/PARDI/Others/MAA05412/EX1/EX2/260325/290925Applied Sep 2024; approved Mar 2025
PR/GJ/VALSAD/PARDI/Others/MAA05412/EX1/EX3/290526/290926Applied Mar 2026; approved May 2026

Documents filed45

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VALSAD/PARDI/Others/MAA05412/EX1/EX3/290526/290926 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)20 May 2026
Architect's certificate (Form 1)30 Mar 2026
Engineer's certificate (Form 2)30 Mar 2026
Engineer's certificate annexure30 Mar 2026
Site photograph, WING A30 Mar 2026
Site photograph, WING B30 Mar 2026
Site photograph, WING C30 Mar 2026
Site photograph, WING D30 Mar 2026
RERA registration certificate10 May 2019
Extension certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Valsad

49%of this project is bookeddistrict median 45%
23%of Valsad projects moved their completion datethis one moved by 36 months

Computed across the 390+ Valsad projects on ReraGenie, from their own filings.

Keep THE CENTRAL HOME & RETAILS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vapi390+ in Valsad

2 kmTHE CENTRAL HOME & RETAIOther 110Dot size: filed unitsN

Filed coordinates, straight-line distance. 110 registered projects within 2 km.

Builder: PARAM INFRA SPACE Partnership Firm

PARAM INFRA SPACE Partnership Firm has 1 registration on GujRERA, including THE CENTRAL HOME & RETAILS. Read the full track record. See more projects on the Valsad district page.

Frequently asked questions

What are my rights if THE CENTRAL HOME & RETAILS is delayed beyond 29 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of THE CENTRAL HOME & RETAILS?

The registered promoter entity is PARAM INFRA SPACE Partnership Firm, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in THE CENTRAL HOME & RETAILS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at THE CENTRAL HOME & RETAILS?

The professionals named in the filing: Architect: DEVDATT MAYUR PANDYA; Engineer: JAYKUMAR ASSUDANI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE CENTRAL HOME & RETAILS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE CENTRAL HOME & RETAILS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE CENTRAL HOME & RETAILS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.