ReraGenieLog inGet a buyer report

Home / Browse projects / Surat, Gujarat / TEXTILE TRADE LINK

Valid until 30 Jun 2022 Commercial project

TEXTILE TRADE LINK

By SHAH DEVELOPERS

RG-GJ-40799 · RERA PR/GJ/SURAT/SURAT CITY/SUDA/CAA01968/EX4/290622 · Last updated on GujRERA portal: 12 Sep 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 44 months
  • 4 extensions taken

Clear

  • Nothing verified clear yet
Jun 2022Possession promisedmoved 44 months from the original
8 of 9Construction stages donefurthest along: Stilt Floor, 0%
13 of 81Units unsoldnot recorded sold or booked
Jump to the 37 documents Report an error

TEXTILE TRADE LINK is a Commercial project by SHAH DEVELOPERS in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/SUDA/CAA01968/EX4/290622 on 12 Mar 2018. Possession is promised by 30 Jun 2022. The completion date has moved by 44 months from the original filing. 68 of the 81 units on this registration are recorded sold or booked, and 8 of 9 construction stages are filed complete.

At a glance

Project

  • NameTEXTILE TRADE LINK
  • TypeCommercial
  • Location
    • DUMBHAL
    • MODEL TOWN TO LIMBAYAT ROAD
    • OPP. NARAYAN NAGAR
    • DEAR DUMBHAL FIRE STATION/KHADI BRIDGE
    • Limbayat
    • Surat City
    • Surat
    • 394210
  • Pincode394210
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/SUDA/CAA01968/EX4/290622
  • ReraGenie IDRG-GJ-40799

Builder

  • NameSHAH DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMar 2018First promiseOct 2018Revised toJun 2022

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2022
  • Registered on12 Mar 2018
  • Promised completion30 Jun 2022
  • Revised completionRevised to 30 Jun 2022 (originally 31 Oct 2018)
  • Buildings1 building record
  • Documents filed37 files

Current status

84%68 of 81 units booked
85.8%Of the estimated cost spent so far

Figures as on 12 Sep 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1---08181

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 12 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 9 construction stages are filed complete. The stage furthest along is Stilt Floor, at 0%.

1: 89% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 12 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingNoNot applicable
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesNoNot applicable
Emergency evacuationYes100%
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,540 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 11.33 cr
Cost incurredRs 9.73 cr
Spent of the estimate85.84%
BuildingWingEstimatedIncurred
1NARs 11.33 crRs 9.73 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANJAY JOSHI
EngineerJALILBHAI ABDULBHAI SHEIKH

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/SURAT CITY/SUDA/CAA01968/EX1/210119Applied Sep 2018; approved Jan 2019
PR/GJ/SURAT/SURAT CITY/SUDA/CAA01968/EX2/230719Applied Jul 2019; approved Jul 2019
PR/GJ/SURAT/SURAT CITY/SUDA/CAA01968/EX3/170221Applied Jan 2021; approved Feb 2021
PR/GJ/SURAT/SURAT CITY/SUDA/CAA01968/EX4/290622Applied Jun 2022; approved Jun 2022

Documents filed37

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/SUDA/CAA01968/EX4/290622 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)12 Sep 2025
Architect's certificate (Form 1)26 Aug 2025
Site photograph, 121 Aug 2025
Site photograph, 121 Aug 2025
Engineer's certificate (Form 2)2 Apr 2019
RERA registration certificate12 Mar 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

84%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 44 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep TEXTILE TRADE LINK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Limbayat2,600+ in Surat

2 kmTEXTILE TRADE LINKOther 50Dot size: filed unitsN

Filed coordinates, straight-line distance. 50 registered projects within 2 km.

Builder: SHAH DEVELOPERS

SHAH DEVELOPERS has 1 registration on GujRERA, including TEXTILE TRADE LINK. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if TEXTILE TRADE LINK is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of TEXTILE TRADE LINK?

The registered promoter entity is SHAH DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in TEXTILE TRADE LINK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at TEXTILE TRADE LINK?

The professionals named in the filing: Architect: SANJAY JOSHI; Engineer: JALILBHAI ABDULBHAI SHEIKH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TEXTILE TRADE LINK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TEXTILE TRADE LINK. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TEXTILE TRADE LINK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.