ReraGenieLog inGet a buyer report

Home / Browse projects / Ahmedabad, Gujarat / Takshashila Air

Valid until 31 Dec 2020 Residential/Group Housing project

Takshashila Air

By TAKSHASHILA CORPORATION LLP

RG-GJ-04627 · RERA PR/GJ/AHMEDABAD/AHMADABAD CITY/AUDA/RAA00058/A1R/EX1/170120 · Last updated on GujRERA portal: 2 Dec 2020

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Dec 2020Possession promisedmoved 12 months from the original
16 of 18Construction stages doneacross 2 buildings; furthest along: Installation of lifts, 95%
95 of 196Units unsoldnot recorded sold or booked
Jump to the 39 documents Report an error

Takshashila Air is a Residential/Group Housing project by TAKSHASHILA CORPORATION LLP in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMADABAD CITY/AUDA/RAA00058/A1R/EX1/170120 on 2 Sep 2017. Possession is promised by 31 Dec 2020. The completion date has moved by 12 months from the original filing. 101 of the 196 units on this registration are recorded sold or booked, and 16 of 18 construction stages are filed complete.

At a glance

Project

  • NameTakshashila Air
  • TypeResidential/Group Housing
  • Location
    • plot no 560 B/h Town hall
    • Ellisbridge
    • Ahmedabad
    • Ellis Bridge
    • Ahmedabad City
    • Ahmedabad
    • 380006
  • Pincode380006
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMADABAD CITY/AUDA/RAA00058/A1R/EX1/170120
  • ReraGenie IDRG-GJ-04627

Builder

  • NameTAKSHASHILA CORPORATION LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM

Key dates

this monthRegisteredSep 2017First promiseDec 2019Revised toDec 2020

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2020
  • Registered on2 Sep 2017
  • Promised completion31 Dec 2020
  • Revised completionRevised to 31 Dec 2020 (originally 31 Dec 2019)
  • Buildings2 building records
  • Documents filed39 files

Current status

52%101 of 196 units booked
100.0%Of the estimated cost spent so far

Figures as on 2 Dec 2020, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower A---1000100
Tower B---96096

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 2 Dec 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of lifts, at 95%.

Tower A100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Tower B91%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%

Progress on shared amenities19

As on 2 Dec 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,683 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 67.94 cr
Cost incurredRs 67.94 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
Tower ANARs 33.97 crRs 33.97 cr
Tower BNARs 33.97 crRs 33.97 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDesigners combine
EngineerMahimatura Consultants pvt ltd

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMADABAD CITY/AUDA/RAA00058/A1R/EX1/170120Applied Dec 2019; approved Jan 2020

Documents filed39

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMADABAD CITY/AUDA/RAA00058/A1R/EX1/170120 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)2 Dec 2020
Architect's certificate (Form 1)28 Nov 2020
Engineer's certificate (Form 2)28 Nov 2020
Engineer's certificate annexure28 Nov 2020
Site photograph, Tower A28 Nov 2020
Site photograph, Tower B28 Nov 2020
RERA registration certificate2 Sep 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

52%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 12 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep Takshashila Air on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ellis Bridge5,400+ in Ahmedabad

2 kmTakshashila AirOther 245Dot size: filed unitsN

Filed coordinates, straight-line distance. 245 registered projects within 2 km.

Builder: TAKSHASHILA CORPORATION LLP

TAKSHASHILA CORPORATION LLP has 1 registration on GujRERA, including Takshashila Air. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if Takshashila Air is delayed beyond 31 Dec 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Takshashila Air?

The registered promoter entity is TAKSHASHILA CORPORATION LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Takshashila Air?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Takshashila Air?

The professionals named in the filing: Architect: Designers combine; Engineer: Mahimatura Consultants pvt ltd. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Takshashila Air?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Takshashila Air. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Takshashila Air to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.