ReraGenieLog inGet a buyer report

Home / Browse projects / Ahmedabad, Gujarat / SWASTHI

Valid until 30 Sep 2023 Mixed Development project

SWASTHI

By SWETRAJ PROJECTS LIMITED LIABILITY PARTNERSHIP

RG-GJ-37878 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA06447/A1M/310820 · Last updated on GujRERA portal: 7 Jul 2022

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Sep 2023Possession promisedno revision filed
8 of 9Construction stages donefurthest along: Sanitary fittings within the flats, 0%
21 of 59Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

SWASTHI is a Mixed Development project by SWETRAJ PROJECTS LIMITED LIABILITY PARTNERSHIP in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA06447/A1M/310820 on 11 Dec 2019. Possession is promised by 30 Sep 2023. 38 of the 59 units on this registration are recorded sold or booked, and 8 of 9 construction stages are filed complete.

At a glance

Project

  • NameSWASTHI
  • TypeMixed Development
  • Location
    • NEAR DIVYA JYOT SCHOOL
    • NEAR KAVERI PRATHAM
    • SHILAJ
    • Shilaj
    • Ahmedabad City
    • Ahmedabad
    • 380058
  • Pincode380058
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA06447/A1M/310820
  • ReraGenie IDRG-GJ-37878

Builder

  • NameSWETRAJ PROJECTS LIMITED LIABILITY PARTNERSHIP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM

Key dates

this monthRegisteredDec 2019PromisedSep 2023

Key facts

Registration and timeline

  • StatusValid until 30 Sep 2023
  • Registered on11 Dec 2019
  • Promised completion30 Sep 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed41 files

Current status

64%38 of 59 units booked
100.0%Of the estimated cost spent so far

Figures as on 7 Jul 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---52759

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 7 Jul 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 9 construction stages are filed complete. The stage furthest along is Sanitary fittings within the flats, at 0%.

A: 89% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 7 Jul 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,664 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 7.21 cr
Cost incurredRs 7.21 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 7.21 crRs 7.21 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIRAL BHAYCHANDBHAI PATEL
EngineerMacwan Nelson Nanubhai

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA06447/A1M/310820 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)7 Jul 2022
Engineer's certificate (Form 2)7 Jul 2022
Engineer's certificate annexure7 Jul 2022
Accountant's certificate (Form 3)7 Jul 2022
Site photograph, A7 Jul 2022
RERA registration certificate11 Dec 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

64%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep SWASTHI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Shilaj5,400+ in Ahmedabad

2 kmSWASTHIOther 197Dot size: filed unitsN

Filed coordinates, straight-line distance. 197 registered projects within 2 km.

Builder: SWETRAJ PROJECTS LIMITED LIABILITY PARTNERSHIP

SWETRAJ PROJECTS LIMITED LIABILITY PARTNERSHIP has 1 registration on GujRERA, including SWASTHI. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if SWASTHI is delayed beyond 30 Sep 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SWASTHI?

The registered promoter entity is SWETRAJ PROJECTS LIMITED LIABILITY PARTNERSHIP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SWASTHI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SWASTHI?

The professionals named in the filing: Architect: VIRAL BHAYCHANDBHAI PATEL; Engineer: Macwan Nelson Nanubhai. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SWASTHI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SWASTHI. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SWASTHI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.