Valid until 30 Sep 2021 Residential/Group Housing project

SWARA DIVINE

By SAVINAY DEVELOPERS

RG-GJ-34896 · RERA PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/RAA01375/200118 · Last updated on GujRERA portal: 21 Oct 2020

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Sep 2021Possession promisedno revision filed
10 of 10Construction stages doneevery applicable stage filed complete
1 of 20Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

SWARA DIVINE is a Residential/Group Housing project by SAVINAY DEVELOPERS in Bhavnagar, Gujarat, registered with GujRERA as PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/RAA01375/200118 on 20 Jan 2018. Possession is promised by 30 Sep 2021. 19 of the 20 units on this registration are recorded sold or booked, and 10 of 10 construction stages are filed complete.

At a glance

Project

  • NameSWARA DIVINE
  • TypeResidential/Group Housing
  • Location
    • PLOT NO 25 A-C SATYANARAYAN ROAD
    • OPP SATYANARAYAN TEMPLE
    • Bhavnagar
    • 364001
  • Pincode364001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/RAA01375/200118
  • ReraGenie IDRG-GJ-34896

Builder

  • NameSAVINAY DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations3 more →

Key dates

this monthRegisteredJan 2018PromisedSep 2021

Key facts

Registration and timeline

  • StatusValid until 30 Sep 2021
  • Registered on20 Jan 2018
  • Promised completion30 Sep 2021
  • Revised completionNone
  • Buildings1 building record
  • Documents filed38 files

Current status

95%19 of 20 units booked
108.6%Of the estimated cost spent so far

Figures as on 21 Oct 2020, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Swara Divine---20020

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 21 Oct 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 10 construction stages are filed complete.

Swara Divine: 100% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 21 Oct 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsNoNot applicable
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingNoNot applicable
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,039 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 5.25 cr
Cost incurredRs 5.70 cr
Spent of the estimate108.57%
BuildingWingEstimatedIncurred
Swara DivineNARs 5.25 crRs 5.70 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHEMAL BHATT
EngineerBHAVESH VYAS

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/RAA01375/200118 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)21 Oct 2020
Engineer's certificate (Form 2)21 Oct 2020
Engineer's certificate annexure21 Oct 2020
Accountant's certificate (Form 3)21 Oct 2020
Site photograph, Swara Divine21 Oct 2020
RERA registration certificate20 Jan 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Bhavnagar

95%of this project is bookeddistrict median 50%
16%of Bhavnagar projects moved their completion datethis one has not

Computed across the 730+ Bhavnagar projects on ReraGenie, from their own filings.

Keep SWARA DIVINE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bhavnagar730+ in Bhavnagar

2 kmSWARA DIVINEOther 248Dot size: filed unitsN

Filed coordinates, straight-line distance. 248 registered projects within 2 km.

Builder: SAVINAY DEVELOPERS

SAVINAY DEVELOPERS has 4 registrations on GujRERA, including SWARA PARKLANE and SWARA DIVINE. Read the full track record. See more projects on the Bhavnagar district page.

Frequently asked questions

What are my rights if SWARA DIVINE is delayed beyond 30 Sep 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SWARA DIVINE?

The registered promoter entity is SAVINAY DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SWARA DIVINE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SWARA DIVINE?

The professionals named in the filing: Architect: HEMAL BHATT; Engineer: BHAVESH VYAS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SWARA DIVINE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SWARA DIVINE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SWARA DIVINE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.