Home / Browse projects / Surat, Gujarat / Swagat Texking

Valid until 29 Oct 2027 Commercial project

Swagat Texking

By SWAGAT DEVELOPER

RG-GJ-44651 · RERA PR/GJ/SURAT/CHORASI/SUDA/CAA01081/EX2/EX3/020326/290626 · Last updated on GujRERA portal: 5 Feb 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 52 months
  • 4 extensions taken

Clear

  • Nothing verified clear yet
Oct 2027Possession promisedmoved 52 months from the original
3 of 9Construction stages donefurthest along: Internal walls, 75%
361 of 378Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

Swagat Texking is a Commercial project by SWAGAT DEVELOPER in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/CHORASI/SUDA/CAA01081/EX2/EX3/020326/290626 on 21 Dec 2017. Possession is promised by 29 Oct 2027. The completion date has moved by 52 months from the original filing. 17 of the 378 units on this registration are recorded sold or booked, and 3 of 9 construction stages are filed complete.

At a glance

Project

  • NameSwagat Texking
  • TypeCommercial
  • Location
    • T.P.35
    • Block No. 223/B
    • F.P.15
    • Kumbharia
    • Kumbhariya
    • Chorasi
    • Surat
    • 395012
  • Pincode395012
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/CHORASI/SUDA/CAA01081/EX2/EX3/020326/290626
  • ReraGenie IDRG-GJ-44651

Builder

  • NameSWAGAT DEVELOPER
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredDec 2017First promiseJun 2023Revised toOct 2027

Key facts

Registration and timeline

  • StatusValid until 29 Oct 2027
  • Registered on21 Dec 2017
  • Promised completion29 Oct 2027
  • Revised completionRevised to 29 Oct 2027 (originally 30 Jun 2023)
  • Buildings1 building record
  • Documents filed41 files

Current status

4%17 of 378 units booked
58.1%Of the estimated cost spent so far

Figures as on 5 Feb 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1---0378378

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 5 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 9 construction stages are filed complete. The stage furthest along is Internal walls, at 75%.

1: 46% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks35%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 5 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingNoNot applicable
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,163 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 68.55 cr
Cost incurredRs 39.83 cr
Spent of the estimate58.1%
BuildingWingEstimatedIncurred
1NARs 68.55 crRs 39.83 cr

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/CHORASI/SUDA/CAA01081/EX1/180523Applied Jan 2023; approved May 2023
PR/GJ/SURAT/CHORASI/SUDA/CAA01081/EX2/281024/290625Applied May 2024; approved Oct 2024
PR/GJ/SURAT/CHORASI/SUDA/CAA01081/EX2/EX3/020326/290626Applied Jun 2025; approved Mar 2026
ExtensionApplied Jun 2026; no approval date filed

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/CHORASI/SUDA/CAA01081/EX2/EX3/020326/290626 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)5 Feb 2026
Engineer's certificate (Form 2)5 Feb 2026
Engineer's certificate annexure5 Feb 2026
Accountant's certificate (Form 3)5 Feb 2026
Site photograph, 15 Feb 2026
Site photograph, 15 Feb 2026
Site photograph, 15 Feb 2026
Site photograph, 15 Feb 2026
Site photograph, 15 Feb 2026
RERA registration certificate21 Dec 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

4%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 52 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep Swagat Texking on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kumbhariya2,600+ in Surat

2 kmSwagat TexkingOther 113Dot size: filed unitsN

Filed coordinates, straight-line distance. 113 registered projects within 2 km.

Builder: SWAGAT DEVELOPER

SWAGAT DEVELOPER has 1 registration on GujRERA, including Swagat Texking. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if Swagat Texking is delayed beyond 29 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Swagat Texking?

The registered promoter entity is SWAGAT DEVELOPER, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Swagat Texking?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in Swagat Texking?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Swagat Texking. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Swagat Texking to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.