Home / Browse projects / Mehsana, Gujarat / Suvidhi Park

Valid until 31 Dec 2026 Residential/Group Housing project

Suvidhi Park

By SUVIDHI PROCON PRIVATE LIMITED

RG-GJ-12408 · RERA PR/GJ/MEHSANA/VIJAPUR/Others/RAA08804/EX1/250526/311226 · Last updated on GujRERA portal: 22 Jun 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 21 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Dec 2026Possession promisedmoved 21 months from the original
0 of 9Construction stages donefurthest along: Slabs of Super Structure, 95%
48 of 142Units unsoldnot recorded sold or booked
Jump to the 42 documents Report an error

Suvidhi Park is a Residential/Group Housing project by SUVIDHI PROCON PRIVATE LIMITED in Mehsana, Gujarat, registered with GujRERA as PR/GJ/MEHSANA/VIJAPUR/Others/RAA08804/EX1/250526/311226 on 23 Jul 2021. Possession is promised by 31 Dec 2026. The completion date has moved by 21 months from the original filing. 94 of the 142 units on this registration are recorded sold or booked, and 0 of 9 construction stages are filed complete.

At a glance

Project

  • NameSuvidhi Park
  • TypeResidential/Group Housing
  • Location
    • Suvidhi Park
    • Near Panjarapole
    • Vijapur
    • Himmatnagar Highway
    • Vijapur
    • Vijapur
    • Mehsana
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/MEHSANA/VIJAPUR/Others/RAA08804/EX1/250526/311226
  • ReraGenie IDRG-GJ-12408

Builder

  • NameSUVIDHI PROCON PRIVATE LIMITED
  • Entity typeCOMPANY
  • Other registrations1 more →

Key dates

this monthRegisteredJul 2021First promiseMar 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2026
  • Registered on23 Jul 2021
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Mar 2025)
  • Buildings1 building record
  • Documents filed42 files

Current status

66%94 of 142 units booked
70.3%Of the estimated cost spent so far

Figures as on 22 Jun 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---1420142

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 22 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 9 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 95%.

A: 78% average across the applicable activities

ActivityProgress
Excavation85%
Podiums (if any)Not applicable
Plinth94%
Stilt Floor0%
Slabs of Super Structure95%
Internal walls, internal plaster, floorings, doors and windows within flats90%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing85%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing77%

Progress on shared amenities19

As on 22 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes85%
Water supplyYes80%
Sewerage (chamber, lines, septic tank, STP)Yes85%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes80%
Street lightingYes90%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area28,101 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 11.00 cr
Cost incurredRs 7.73 cr
Spent of the estimate70.27%
BuildingWingEstimatedIncurred
ANARs 11.00 crRs 7.73 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHarsh S Patel
EngineerAakash S Jain

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/MEHSANA/VIJAPUR/Others/RAA08804/EX1/250526/311226Applied Dec 2025; approved May 2026

Documents filed42

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/MEHSANA/VIJAPUR/Others/RAA08804/EX1/250526/311226 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)22 Jun 2026
Engineer's certificate (Form 2)22 Jun 2026
Engineer's certificate annexure22 Jun 2026
Accountant's certificate (Form 3)22 Jun 2026
Site photograph, A16 Jun 2026
RERA registration certificate23 Jul 2021
Extension certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Mehsana

66%of this project is bookeddistrict median 54%
11%of Mehsana projects moved their completion datethis one moved by 21 months

Computed across the 200+ Mehsana projects on ReraGenie, from their own filings.

Keep Suvidhi Park on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Mehsana200+ in Mehsana

Builder: SUVIDHI PROCON PRIVATE LIMITED

SUVIDHI PROCON PRIVATE LIMITED has 2 registrations on GujRERA, including Suvidhi Park and Suvidhi Park. Read the full track record. See more projects on the Mehsana district page.

Frequently asked questions

What are my rights if Suvidhi Park is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Suvidhi Park?

The registered promoter entity is SUVIDHI PROCON PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Suvidhi Park?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Suvidhi Park?

The professionals named in the filing: Architect: Harsh S Patel; Engineer: Aakash S Jain. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Suvidhi Park?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Suvidhi Park. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Suvidhi Park to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.