ReraGenieLog inGet a buyer report

Home / Browse projects / Rajkot, Gujarat / SUNRISE PALLADIUM

Valid until 30 Apr 2029 Mixed Development project

SUNRISE PALLADIUM

By SUNRISE PALLADIUM

RG-GJ-26640 · RERA PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/MAA14341/281024/311228 · Last updated on GujRERA portal: 6 Jun 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2029Possession promisedno revision filed
8 of 18Construction stages doneacross 2 buildings; furthest along: Staircases, 95%
40 of 91Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

SUNRISE PALLADIUM is a Mixed Development project by SUNRISE PALLADIUM in Rajkot, Gujarat, registered with GujRERA as PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/MAA14341/281024/311228 on 28 Oct 2024. Possession is promised by 30 Apr 2029. 51 of the 91 units on this registration are recorded sold or booked, and 8 of 18 construction stages are filed complete.

At a glance

Project

  • NameSUNRISE PALLADIUM
  • TypeMixed Development
  • Location
    • SUNRISE PALLADIUM
    • NEAR SUNRISE PRIME
    • NEW 150 FEET RING ROAD
    • GHANTESHWAR
    • RAJKOT
    • GHANTESHWAR
    • Rajkot
    • 360006
  • Pincode360006
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/MAA14341/281024/311228
  • ReraGenie IDRG-GJ-26640

Builder

  • NameSUNRISE PALLADIUM
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredOct 2024PromisedApr 2029

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2029
  • Registered on28 Oct 2024
  • Promised completion30 Apr 2029
  • Revised completionNone
  • Buildings2 building records
  • Documents filed38 files

Current status

56%51 of 91 units booked
78.0%Of the estimated cost spent so far

Figures as on 6 Jun 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B---28028
A---54963

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 6 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 95%.

B77%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats94%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing30%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%
A82%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats94%
Sanitary fittings within the flats70%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing45%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing30%

Progress on shared amenities19

As on 6 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes15%
Water supplyYes70%
Sewerage (chamber, lines, septic tank, STP)Yes65%
Storm water drainsYes20%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,484 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 17.75 cr
Cost incurredRs 13.85 cr
Spent of the estimate78.03%
BuildingWingEstimatedIncurred
ANARs 10.75 crRs 8.60 cr
BNARs 7.00 crRs 5.25 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNiravkumar Sureshbhai Khant
EngineerVARUNBHAI KISHORBHAI SUCHAK

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/MAA14341/281024/311228 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)6 Jun 2026
Architect's certificate (Form 1)5 Jun 2026
Engineer's certificate (Form 2)5 Jun 2026
Engineer's certificate annexure5 Jun 2026
Site photograph, B5 Jun 2026
Site photograph, A5 Jun 2026
RERA registration certificate28 Oct 2024
Proforma agreement for sale-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Rajkot

56%of this project is bookeddistrict median 56%
13%of Rajkot projects moved their completion datethis one has not

Computed across the 1,800+ Rajkot projects on ReraGenie, from their own filings.

Keep SUNRISE PALLADIUM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near GHANTESHWAR1,800+ in Rajkot

2 kmSUNRISE PALLADIUMOther 84Dot size: filed unitsN

Filed coordinates, straight-line distance. 84 registered projects within 2 km.

Builder: SUNRISE PALLADIUM

SUNRISE PALLADIUM has 1 registration on GujRERA, including SUNRISE PALLADIUM. Read the full track record. See more projects on the Rajkot district page.

Frequently asked questions

What are my rights if SUNRISE PALLADIUM is delayed beyond 30 Apr 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SUNRISE PALLADIUM?

The registered promoter entity is SUNRISE PALLADIUM, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SUNRISE PALLADIUM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SUNRISE PALLADIUM?

The professionals named in the filing: Architect: Niravkumar Sureshbhai Khant; Engineer: VARUNBHAI KISHORBHAI SUCHAK. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUNRISE PALLADIUM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUNRISE PALLADIUM. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUNRISE PALLADIUM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.