Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Oct 2026Possession promisedmoved 12 months from the original
55 of 63Construction stages doneacross 7 buildings; furthest along: External plumbing and external plaster, 95%
215 of 373Units unsoldnot recorded sold or booked
Jump to the 48 documents Report an error

SUNCITY PLUS is a Mixed Development project by OM DEVELOPERS in Rajkot, Gujarat, registered with GujRERA as PR/GJ/RAJKOT/RAJKOT/Others/MAA08380/EX1/091225/181026 on 27 Apr 2021. Possession is promised by 18 Oct 2026. The completion date has moved by 12 months from the original filing. 158 of the 373 units on this registration are recorded sold or booked, and 55 of 63 construction stages are filed complete.

At a glance

Project

  • NameSUNCITY PLUS
  • TypeMixed Development
  • Location
    • 80 FEET ROAD
    • NEAR RAMAPIR CHOWKDI
    • OFF. 150 FEET RING ROAD
    • RAIYA DHAR
    • Rajkot
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/RAJKOT/RAJKOT/Others/MAA08380/EX1/091225/181026
  • ReraGenie IDRG-GJ-67813

Builder

  • NameOM DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations36 more →

Key dates

this monthRegisteredApr 2021First promiseOct 2025Revised toOct 2026

Key facts

Registration and timeline

  • StatusValid until 18 Oct 2026
  • Registered on27 Apr 2021
  • Promised completion18 Oct 2026
  • Revised completionRevised to 18 Oct 2026 (originally 18 Oct 2025)
  • Buildings7 building records
  • Documents filed48 files

Current status

42%158 of 373 units booked
96.9%Of the estimated cost spent so far

Figures as on 2 Dec 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER C---50050
TOWER D---50050
TOWER E---52052
TOWER F---51051
TOWER G---501060
TOWER A---501060
TOWER B---50050

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building7

As on 2 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

55 of 63 construction stages are filed complete across 7 buildings. The stage furthest along is External plumbing and external plaster, at 95%.

TOWER C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER E100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER F100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER G88%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats75%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing40%
TOWER A92%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%
TOWER B94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%

Progress on shared amenities19

As on 2 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes50%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes50%
Storm water drainsYes50%
Landscaping and tree plantingYes40%
Street lightingNoNot applicable
Community buildingsYes40%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes50%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes50%
Fire fightingYes50%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes50%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,845 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 20.62 cr
Cost incurredRs 19.99 cr
Spent of the estimate96.91%
BuildingWingEstimatedIncurred
TOWER ANARs 2.95 crRs 2.86 cr
TOWER BNARs 2.95 crRs 2.86 cr
TOWER CNARs 2.95 crRs 2.86 cr
TOWER DNARs 2.95 crRs 2.86 cr
TOWER ENARs 2.95 crRs 2.86 cr
TOWER FNARs 2.95 crRs 2.86 cr
TOWER GNARs 2.95 crRs 2.86 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCHIRAG G. TANTI
EngineerDHARMESH H GEDIYA

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/RAJKOT/RAJKOT/Others/MAA08380/EX1/091225/181026Applied Sep 2025; approved Dec 2025

Documents filed48

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/RAJKOT/RAJKOT/Others/MAA08380/EX1/091225/181026 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)2 Dec 2025
Engineer's certificate (Form 2)2 Dec 2025
Engineer's certificate annexure2 Dec 2025
Accountant's certificate (Form 3)2 Dec 2025
Site photograph, TOWER C2 Dec 2025
Site photograph, TOWER D2 Dec 2025
Site photograph, TOWER E2 Dec 2025
Site photograph, TOWER F2 Dec 2025
Site photograph, TOWER G2 Dec 2025
Site photograph, TOWER A2 Dec 2025
Site photograph, TOWER B2 Dec 2025
RERA registration certificate27 Apr 2021
Extension certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Rajkot

42%of this project is bookeddistrict median 56%
13%of Rajkot projects moved their completion datethis one moved by 12 months

Computed across the 1,800+ Rajkot projects on ReraGenie, from their own filings.

Keep SUNCITY PLUS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Rajkot1,800+ in Rajkot

2 kmSUNCITY PLUSOther 207Dot size: filed unitsN

Filed coordinates, straight-line distance. 207 registered projects within 2 km.

Builder: OM DEVELOPERS

OM DEVELOPERS has 37 registrations on GujRERA, including SARTHAK HABITAT and SAKAR EAST. Read the full track record. See more projects on the Rajkot district page.

Frequently asked questions

What are my rights if SUNCITY PLUS is delayed beyond 18 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SUNCITY PLUS?

The registered promoter entity is OM DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SUNCITY PLUS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SUNCITY PLUS?

The professionals named in the filing: Architect: CHIRAG G. TANTI; Engineer: DHARMESH H GEDIYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUNCITY PLUS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUNCITY PLUS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUNCITY PLUS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.