ReraGenieLog inGet a buyer report

Home / Browse projects / Valsad, Gujarat / sun signature 2

Valid until 30 Apr 2027 Residential/Group Housing project

sun signature 2

By S8 DEVELOPERS

RG-GJ-47328 · RERA PR/GJ/VALSAD/PARDI/Others/RAA09588/271221 · Last updated on GujRERA portal: 22 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2027Possession promisedno revision filed
6 of 9Construction stages donefurthest along: Sanitary fittings within the flats, 96%
7 of 161Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

sun signature 2 is a Residential/Group Housing project by S8 DEVELOPERS in Valsad, Gujarat, registered with GujRERA as PR/GJ/VALSAD/PARDI/Others/RAA09588/271221 on 27 Dec 2021. Possession is promised by 30 Apr 2027. 154 of the 161 units on this registration are recorded sold or booked, and 6 of 9 construction stages are filed complete.

At a glance

Project

  • Namesun signature 2
  • TypeResidential/Group Housing
  • Location
    • dungra
    • vapi
    • Pardi
    • Valsad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VALSAD/PARDI/Others/RAA09588/271221
  • ReraGenie IDRG-GJ-47328

Builder

  • NameS8 DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations2 more →

Key dates

this monthRegisteredDec 2021PromisedApr 2027

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2027
  • Registered on27 Dec 2021
  • Promised completion30 Apr 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed38 files

Current status

96%154 of 161 units booked
68.2%Of the estimated cost spent so far

Figures as on 22 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
EFG---1610161

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 22 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 9 construction stages are filed complete. The stage furthest along is Sanitary fittings within the flats, at 96%.

EFG: 98% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats96%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing96%

Progress on shared amenities23

As on 22 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes40%
Water supplyYes70%
Sewerage (chamber, lines, septic tank, STP)Yes70%
Storm water drainsYes20%
Landscaping and tree plantingYes10%
Street lightingYes20%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes30%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%
Compound wallYes70%
Plinth protectionYes30%
Water tankYes70%
Other requirementsYes50%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,094 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 14.33 cr
Cost incurredRs 9.78 cr
Spent of the estimate68.2%
BuildingWingEstimatedIncurred
EFGNARs 14.33 crRs 9.78 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAR.VARUN HADIA
EngineerSAGAR K JILARIYA

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VALSAD/PARDI/Others/RAA09588/271221 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)22 Oct 2024
Engineer's certificate annexure22 Oct 2024
RERA registration certificate27 Dec 2021
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Valsad

96%of this project is bookeddistrict median 45%
23%of Valsad projects moved their completion datethis one has not

Computed across the 390+ Valsad projects on ReraGenie, from their own filings.

Keep sun signature 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Valsad390+ in Valsad

2 kmsun signature 2Other 81Dot size: filed unitsN

Filed coordinates, straight-line distance. 81 registered projects within 2 km.

Builder: S8 DEVELOPERS

S8 DEVELOPERS has 3 registrations on GujRERA, including SUN SIGNATURE 2 and sun signature 2. Read the full track record. See more projects on the Valsad district page.

Frequently asked questions

What are my rights if sun signature 2 is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of sun signature 2?

The registered promoter entity is S8 DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in sun signature 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at sun signature 2?

The professionals named in the filing: Architect: AR.VARUN HADIA; Engineer: SAGAR K JILARIYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in sun signature 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About sun signature 2. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save sun signature 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.