SUN SHINE SQUARE

By SAI DEVELOPERS

RG-GJ-10694 · RERA PR/GJ/MEHSANA/VISNAGAR/Others/CAA06563/EX2/A1C/230222 · Last updated on GujRERA portal: 2 Apr 2024

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Dec 2022Possession promisedmoved 24 months from the original
18 of 27Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 80%
21 of 93Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

SUN SHINE SQUARE is a Commercial project by SAI DEVELOPERS in Mehsana, Gujarat, registered with GujRERA as PR/GJ/MEHSANA/VISNAGAR/Others/CAA06563/EX2/A1C/230222 on 3 Jan 2020. Possession is promised by 31 Dec 2022. The completion date has moved by 24 months from the original filing. 72 of the 93 units on this registration are recorded sold or booked, and 18 of 27 construction stages are filed complete.

At a glance

Project

  • NameSUN SHINE SQUARE
  • TypeCommercial
  • Location
    • R.S.No.3634 (old R.S.No.2341 P 1)
    • Near R.K. Party Plot
    • Kada Cross Rasta
    • Visnagar
    • Mehsana
    • VISNAGAR
    • Visnagar
    • Mehsana
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/MEHSANA/VISNAGAR/Others/CAA06563/EX2/A1C/230222
  • ReraGenie IDRG-GJ-10694

Builder

  • NameSAI DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations20 more →

Key dates

this monthRegisteredJan 2020First promiseDec 2020Revised toDec 2022

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2022
  • Registered on3 Jan 2020
  • Promised completion31 Dec 2022
  • Revised completionRevised to 31 Dec 2022 (originally 30 Dec 2020)
  • Buildings3 building records
  • Documents filed43 files

Current status

77%72 of 93 units booked
92.1%Of the estimated cost spent so far

Figures as on 2 Apr 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---02121
B---04545
C---02727

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 2 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 80%.

A89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C76%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats80%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%

Progress on shared amenities19

As on 2 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,400 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 1.11 cr
Cost incurredRs 1.02 cr
Spent of the estimate92.12%
BuildingWingEstimatedIncurred
BNARs 53.57 lakhRs 53.57 lakh
CNARs 32.43 lakhRs 23.68 lakh
ANARs 25.00 lakhRs 25.00 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDEVANG BABUBHAI VAGHELA
EngineerPRAVINBHAI RANCHHODLAL SHAH

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/MEHSANA/VISNAGAR/Others/CAA06563/EX1/160121Applied Dec 2020; approved Jan 2021
PR/GJ/MEHSANA/VISNAGAR/Others/CAA06563/EX2/A1C/230222Applied Dec 2021; approved Feb 2022

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/MEHSANA/VISNAGAR/Others/CAA06563/EX2/A1C/230222 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)2 Apr 2024
Engineer's certificate annexure2 Apr 2024
Accountant's certificate (Form 3)2 Apr 2024
Architect's certificate (Form 1)27 Mar 2024
Site photograph, A13 Mar 2024
Site photograph, B13 Mar 2024
Site photograph, C13 Mar 2024
RERA registration certificate3 Jan 2020
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Mehsana

77%of this project is bookeddistrict median 54%
11%of Mehsana projects moved their completion datethis one moved by 24 months

Computed across the 200+ Mehsana projects on ReraGenie, from their own filings.

Keep SUN SHINE SQUARE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Visnagar200+ in Mehsana

2 kmSUN SHINE SQUAREOther 13Dot size: filed unitsN

Filed coordinates, straight-line distance. 13 registered projects within 2 km.

Builder: SAI DEVELOPERS

SAI DEVELOPERS has 21 registrations on GujRERA, including ATLANTIS SQUARE and SAI DRASHTI RESIDENCY. Read the full track record. See more projects on the Mehsana district page.

Frequently asked questions

What are my rights if SUN SHINE SQUARE is delayed beyond 31 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SUN SHINE SQUARE?

The registered promoter entity is SAI DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SUN SHINE SQUARE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SUN SHINE SQUARE?

The professionals named in the filing: Architect: DEVANG BABUBHAI VAGHELA; Engineer: PRAVINBHAI RANCHHODLAL SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUN SHINE SQUARE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUN SHINE SQUARE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUN SHINE SQUARE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.