Home / Browse projects / Valsad, Gujarat / SUMUKH TOWNSHIP

Valid until 25 Oct 2027 Residential/Group Housing project

SUMUKH TOWNSHIP

By SHIVAM DEVELOPERS

RG-GJ-72317 · RERA PR/GJ/VALSAD/VALSAD/Others/RAA06855/EX1/230926/251027 · Last updated on GujRERA portal: 1 Sep 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 16 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Oct 2027Possession promisedmoved 16 months from the original
37 of 99Construction stages doneacross 11 buildings; furthest along: Internal walls, 60%
241 of 340Units unsoldnot recorded sold or booked
Jump to the 58 documents Report an error

SUMUKH TOWNSHIP is a Residential/Group Housing project by SHIVAM DEVELOPERS in Valsad, Gujarat, registered with GujRERA as PR/GJ/VALSAD/VALSAD/Others/RAA06855/EX1/230926/251027 on 7 Mar 2020. Possession is promised by 25 Oct 2027. The completion date has moved by 16 months from the original filing. 99 of the 340 units on this registration are recorded sold or booked, and 37 of 99 construction stages are filed complete.

At a glance

Project

  • NameSUMUKH TOWNSHIP
  • TypeResidential/Group Housing
  • Location
    • SHREE NAGAR SOCIETY ROAD
    • HALAR
    • Mogarawadi
    • Valsad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VALSAD/VALSAD/Others/RAA06855/EX1/230926/251027
  • ReraGenie IDRG-GJ-72317

Builder

  • NameSHIVAM DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations45 more →

Key dates

this monthRegisteredMar 2020First promiseJun 2026Revised toOct 2027

Key facts

Registration and timeline

  • StatusValid until 25 Oct 2027
  • Registered on7 Mar 2020
  • Promised completion25 Oct 2027
  • Revised completionRevised to 25 Oct 2027 (originally 30 Jun 2026)
  • Buildings11 building records
  • Documents filed58 files

Current status

29%99 of 340 units booked
53.8%Of the estimated cost spent so far

Figures as on 1 Sep 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
D---20020
E---20020
F---20020
G---20020
H---80080
I---40040
J---40040
K---40040
A---20020
B---20020
C---20020

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building11

As on 1 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

37 of 99 construction stages are filed complete across 11 buildings. The stage furthest along is Internal walls, at 60%.

D0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
E0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
F0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
G0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
H89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
I31%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure50%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
J0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
K56%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing30%
A89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 1 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes65%
Water supplyYes65%
Sewerage (chamber, lines, septic tank, STP)Yes65%
Storm water drainsYes65%
Landscaping and tree plantingYes70%
Street lightingYes65%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes65%
Water conservation, rain water harvestingYes65%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes70%
Fire fightingYes70%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area14,054 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 68.64 cr
Cost incurredRs 36.92 cr
Spent of the estimate53.8%
BuildingWingEstimatedIncurred
HNARs 13.56 crRs 13.56 cr
INARs 6.68 crRs 3.01 cr
JNARs 6.68 cr-
KNARs 6.68 crRs 5.35 cr
ANARs 5.00 crRs 5.00 cr
BNARs 5.00 crRs 5.00 cr
CNARs 5.00 crRs 5.00 cr
DNARs 5.00 cr-
ENARs 5.00 cr-
FNARs 5.00 cr-
GNARs 5.00 cr-

Certifying professionals and partners1

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBHARGAV DESAI

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VALSAD/VALSAD/Others/RAA06855/EX1/230926/251027Applied May 2026; approved Sep 2026

Documents filed58

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VALSAD/VALSAD/Others/RAA06855/EX1/230926/251027 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)1 Sep 2026
Engineer's certificate (Form 2)30 May 2026
Engineer's certificate annexure30 May 2026
Architect's certificate (Form 1)28 May 2026
Site photograph, D23 May 2026
Site photograph, E23 May 2026
Site photograph, F23 May 2026
Site photograph, G23 May 2026
Site photograph, H23 May 2026
Site photograph, H23 May 2026
Site photograph, H23 May 2026
Site photograph, I23 May 2026
Site photograph, J23 May 2026
Site photograph, K23 May 2026
Site photograph, K23 May 2026
Site photograph, K23 May 2026
Site photograph, A23 May 2026
Site photograph, A23 May 2026
Site photograph, B23 May 2026
Site photograph, C23 May 2026
Site photograph, C23 May 2026
Site photograph, C23 May 2026
RERA registration certificate7 Mar 2020
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Valsad

29%of this project is bookeddistrict median 45%
23%of Valsad projects moved their completion datethis one moved by 16 months

Computed across the 390+ Valsad projects on ReraGenie, from their own filings.

Keep SUMUKH TOWNSHIP on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Mogarawadi390+ in Valsad

2 kmSUMUKH TOWNSHIPOther 51Dot size: filed unitsN

Filed coordinates, straight-line distance. 51 registered projects within 2 km.

Builder: SHIVAM DEVELOPERS

SHIVAM DEVELOPERS has 46 registrations on GujRERA, including AARYA ENCLAVE and PUSHPAK EXOTICA. Read the full track record. See more projects on the Valsad district page.

Frequently asked questions

What are my rights if SUMUKH TOWNSHIP is delayed beyond 25 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SUMUKH TOWNSHIP?

The registered promoter entity is SHIVAM DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SUMUKH TOWNSHIP?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SUMUKH TOWNSHIP?

The professionals named in the filing: Architect: BHARGAV DESAI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUMUKH TOWNSHIP?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUMUKH TOWNSHIP. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUMUKH TOWNSHIP to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.