Home / Browse projects / Surat, Gujarat / SUMUKH RESIDENCY

Valid until 30 Jun 2026 Mixed Development project

SUMUKH RESIDENCY

By SHREE MANGALAM ENTERPRISE

RG-GJ-87029 · RERA PR/GJ/SURAT/SURAT CITY/SUDA/MAA04826/EX1/140725/300626 · Last updated on GujRERA portal: 4 Jul 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Jun 2026Possession promisedmoved 12 months from the original
40 of 63Construction stages doneacross 7 buildings; furthest along: Stilt Floor, 90%
170 of 302Units unsoldnot recorded sold or booked
Jump to the 47 documents Report an error

SUMUKH RESIDENCY is a Mixed Development project by SHREE MANGALAM ENTERPRISE in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/SUDA/MAA04826/EX1/140725/300626 on 12 Feb 2019. Possession is promised by 30 Jun 2026. The completion date has moved by 12 months from the original filing. 132 of the 302 units on this registration are recorded sold or booked, and 40 of 63 construction stages are filed complete.

At a glance

Project

  • NameSUMUKH RESIDENCY
  • TypeMixed Development
  • Location
    • BLOCK NO:312
    • O.P.NO:17
    • F.P.NO:17
    • SUB PLOT NO-1
    • SUB PLOT NO :1/1
    • AT T.P.S. NO:62 VILL:DINDOLI
    • TA:UDHNA CITY
    • Dindoli
    • Surat City
    • Surat
    • 394210
  • Pincode394210
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/SUDA/MAA04826/EX1/140725/300626
  • ReraGenie IDRG-GJ-87029

Builder

  • NameSHREE MANGALAM ENTERPRISE
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredFeb 2019First promiseJun 2025Revised toJun 2026

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2026
  • Registered on12 Feb 2019
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2025)
  • Buildings7 building records
  • Documents filed47 files

Current status

44%132 of 302 units booked
98.9%Of the estimated cost spent so far

Figures as on 4 Jul 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MN---38644
AB---401252
CD---40646
EF---40040
GH---40040
IJ---40040
KL---40040

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building7

As on 4 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

40 of 63 construction stages are filed complete across 7 buildings. The stage furthest along is Stilt Floor, at 90%.

MN89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
AB89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
CD89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
EF72%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor90%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats75%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing30%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%
GH72%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor90%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats75%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing30%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%
IJ72%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor90%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats75%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing30%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%
KL72%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor90%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats75%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing30%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%

Progress on shared amenities19

As on 4 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes90%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes70%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes70%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes20%
Electrical meter room, sub-station, receiving stationYes30%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,998 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 19.58 cr
Cost incurredRs 19.36 cr
Spent of the estimate98.89%
BuildingWingEstimatedIncurred
ABNARs 2.88 crRs 2.88 cr
CDNARs 2.79 crRs 2.79 cr
MNNARs 2.79 crRs 2.79 cr
EFNARs 2.78 crRs 2.78 cr
GHNARs 2.78 crRs 2.75 cr
IJNARs 2.78 crRs 2.69 cr
KLNARs 2.78 crRs 2.69 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/SURAT CITY/SUDA/MAA04826/EX1/140725/300626Applied May 2025; approved Jul 2025

Documents filed47

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/SUDA/MAA04826/EX1/140725/300626 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)4 Jul 2025
Engineer's certificate (Form 2)3 Jul 2025
Engineer's certificate annexure3 Jul 2025
Architect's certificate (Form 1)2 Jul 2025
Site photograph, MN2 Jul 2025
Site photograph, AB2 Jul 2025
Site photograph, CD2 Jul 2025
Site photograph, EF2 Jul 2025
Site photograph, GH2 Jul 2025
Site photograph, IJ2 Jul 2025
Site photograph, KL2 Jul 2025
RERA registration certificate12 Feb 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

44%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 12 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep SUMUKH RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dindoli2,600+ in Surat

2 kmSUMUKH RESIDENCYOther 180Dot size: filed unitsN

Filed coordinates, straight-line distance. 180 registered projects within 2 km.

Builder: SHREE MANGALAM ENTERPRISE

SHREE MANGALAM ENTERPRISE has 1 registration on GujRERA, including SUMUKH RESIDENCY. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if SUMUKH RESIDENCY is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SUMUKH RESIDENCY?

The registered promoter entity is SHREE MANGALAM ENTERPRISE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SUMUKH RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in SUMUKH RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUMUKH RESIDENCY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUMUKH RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.