Home / Browse projects / Ahmedabad, Gujarat / Skypark

Valid until 30 Apr 2028 Mixed Development project

Skypark

By VP SKYPARK DEVELOPERS LLP

RG-GJ-72110 · RERA PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Municipal Corporation/MAA14056/280824/311227 · Last updated on GujRERA portal: 6 Aug 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2028Possession promisedno revision filed
6 of 18Construction stages doneacross 2 buildings; furthest along: Internal walls, 60%
149 of 281Units unsoldnot recorded sold or booked
Jump to the 32 documents Report an error

Skypark is a Mixed Development project by VP SKYPARK DEVELOPERS LLP in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Municipal Corporation/MAA14056/280824/311227 on 28 Aug 2024. Possession is promised by 30 Apr 2028. 132 of the 281 units on this registration are recorded sold or booked, and 6 of 18 construction stages are filed complete.

At a glance

Project

  • NameSkypark
  • TypeMixed Development
  • Location
    • SKYPARK
    • NEAR SANVI NIRMAN ESTELLA
    • VIP ROAD
    • BOPAL
    • GHUMA
    • Daskroi
    • Ahmedabad
    • 380058
  • Pincode380058
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Municipal Corporation/MAA14056/280824/311227
  • ReraGenie IDRG-GJ-72110

Builder

  • NameVP SKYPARK DEVELOPERS LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM

Key dates

this monthRegisteredAug 2024PromisedApr 2028

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2028
  • Registered on28 Aug 2024
  • Promised completion30 Apr 2028
  • Revised completionNone
  • Buildings2 building records
  • Documents filed32 files

Current status

47%132 of 281 units booked
58.9%Of the estimated cost spent so far

Figures as on 6 Aug 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C+D+E+F+G---1920192
A+B---602989

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 6 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 60%.

C+D+E+F+G47%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A+B43%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats40%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing10%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 6 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,406 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 67.00 cr
Cost incurredRs 39.44 cr
Spent of the estimate58.87%
BuildingWingEstimatedIncurred
C+D+E+F+GNARs 42.15 crRs 25.36 cr
A+BNARs 24.85 crRs 14.09 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBhaumik Laxmanbhai Patel
EngineerVIREN DILIPBHAI PAREKH

Documents filed32

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/DASKROI/Ahmedabad Municipal Corporation/MAA14056/280824/311227 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)6 Aug 2026
Engineer's certificate (Form 2)30 Jul 2026
Engineer's certificate annexure30 Jul 2026
Architect's certificate (Form 1)29 Jul 2026
Site photograph, C+D+E+F+G29 Jul 2026
Site photograph, A+B29 Jul 2026
RERA registration certificate28 Aug 2024
Proforma agreement for sale-
Auditor's report (3 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Area development document-
Proforma allotment letter-
Brochure-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Property card 2-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

47%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep Skypark on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near GHUMA5,400+ in Ahmedabad

2 kmSkyparkOther 236Dot size: filed unitsN

Filed coordinates, straight-line distance. 236 registered projects within 2 km.

Builder: VP SKYPARK DEVELOPERS LLP

VP SKYPARK DEVELOPERS LLP has 1 registration on GujRERA, including Skypark. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if Skypark is delayed beyond 30 Apr 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Skypark?

The registered promoter entity is VP SKYPARK DEVELOPERS LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Skypark?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Skypark?

The professionals named in the filing: Architect: Bhaumik Laxmanbhai Patel; Engineer: VIREN DILIPBHAI PAREKH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Skypark?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Skypark. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Skypark to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.