Home / Browse projects / Rajkot, Gujarat / SKY HEIGHTS
SKY HEIGHTS
RG-GJ-65615 · RERA PR/GJ/RAJKOT/RAJKOT/Others/RAA02113/A1R/310522 · Last updated on GujRERA portal: 22 Jun 2022
Source: official GujRERA filing
Red flags
- No red flags in this filing
Clear
- Completion date never moved
- Separate project account declared
Saved.
SKY HEIGHTS is a Residential/Group Housing project by SKY DEVELOPERS in Rajkot, Gujarat, registered with GujRERA as PR/GJ/RAJKOT/RAJKOT/Others/RAA02113/A1R/310522 on 22 Mar 2018. Possession is promised by 30 Oct 2022. 264 of the 312 units on this registration are recorded sold or booked, and 54 of 54 construction stages are filed complete.
At a glance
Project
- NameSKY HEIGHTS
- TypeResidential/Group Housing
- Location
- SKY HEIGHTS
- NEAR EAGLE RESIDENCY
- GOVARDHAN CHOWK
- 150 FT RINGROAD
- Rajkot
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/RAJKOT/RAJKOT/Others/RAA02113/A1R/310522
- ReraGenie IDRG-GJ-65615
Builder
- NameSKY DEVELOPERS
- Entity typePARTNERSHIP FIRM
- Other registrations11 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 30 Oct 2022
- Registered on22 Mar 2018
- Promised completion30 Oct 2022
- Revised completionNone
- Buildings6 building records
- Documents filed43 files
Current status
Figures as on 22 Jun 2022, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | - | - | - | 52 | 0 | 52 |
| WING B | - | - | - | 52 | 0 | 52 |
| WING C | - | - | - | 52 | 0 | 52 |
| WING D | - | - | - | 52 | 0 | 52 |
| WING E | - | - | - | 52 | 0 | 52 |
| WING F | - | - | - | 52 | 0 | 52 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building6
As on 22 Jun 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
54 of 54 construction stages are filed complete across 6 buildings.
WING A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
WING B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
WING C100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
WING D100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
WING E100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
WING F100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 22 Jun 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | No | Not applicable |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | Yes | 100% |
| Landscaping and tree planting | Yes | 100% |
| Street lighting | No | Not applicable |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Fire fighting | Yes | 100% |
| Drinking water facilities | No | Not applicable |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 100% |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| WING A | NA | Rs 5.57 cr | Rs 5.57 cr |
| WING B | NA | Rs 5.57 cr | Rs 5.57 cr |
| WING C | NA | Rs 5.57 cr | Rs 5.57 cr |
| WING D | NA | Rs 5.57 cr | Rs 5.57 cr |
| WING E | NA | Rs 5.57 cr | Rs 5.57 cr |
| WING F | NA | Rs 5.57 cr | Rs 5.57 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | CHETAN PANCHOLI |
| Engineer | SANJAY UNJIA |
Documents filed43
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/RAJKOT/RAJKOT/Others/RAA02113/A1R/310522 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect's certificate (Form 1) | 22 Jun 2022 |
| Engineer's certificate (Form 2) | 22 Jun 2022 |
| Engineer's certificate annexure | 22 Jun 2022 |
| Accountant's certificate (Form 3) | 22 Jun 2022 |
| Site photograph, WING A | 22 Jun 2022 |
| Site photograph, WING B | 22 Jun 2022 |
| Site photograph, WING C | 22 Jun 2022 |
| Site photograph, WING D | 22 Jun 2022 |
| Site photograph, WING E | 22 Jun 2022 |
| Site photograph, WING F | 22 Jun 2022 |
| RERA registration certificate | 22 Mar 2018 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Rajkot
Computed across the 1,800+ Rajkot projects on ReraGenie, from their own filings.
Keep SKY HEIGHTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Rajkot1,800+ in Rajkot
Filed coordinates, straight-line distance. 281 registered projects within 2 km.
Rajkot Municipal Corporation Smart Ghar 5 and
RAJKOT MUNICIPAL CORPORATION
West Zone Package 5-15A & 28A
RAJKOT MUNICIPAL CORPORATION
Smart Ghar 3
RAJKOT MUNICIPAL CORPORATION
GHTC-I LHP Rajkot
RAJKOT MUNICIPAL CORPORATION
West Zone Package 3 -FP 41A
RAJKOT MUNICIPAL CORPORATION
SANATAN
SANATAN INFRACON LLP
See every Rajkot project, with the district possession charts
Builder: SKY DEVELOPERS
SKY DEVELOPERS has 12 registrations on GujRERA, including SKY WALK and SKYLINE APPARTMENT. Read the full track record. See more projects on the Rajkot district page.
Frequently asked questions
What are my rights if SKY HEIGHTS is delayed beyond 30 Oct 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of SKY HEIGHTS?
The registered promoter entity is SKY DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in SKY HEIGHTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SKY HEIGHTS?
The professionals named in the filing: Architect: CHETAN PANCHOLI; Engineer: SANJAY UNJIA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SKY HEIGHTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.
Report an error Share feedback