ReraGenieLog inGet a buyer report

Home / Browse projects / Rajkot, Gujarat / SHUBH SANGAM

Valid until 31 May 2027 Mixed Development project

SHUBH SANGAM

By SHUBH REALITIES

RG-GJ-81913 · RERA PR/GJ/RAJKOT/RAJKOT/Others/MAA12343/EX1/EX2/290626/310527 · Last updated on GujRERA portal: 25 May 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
May 2027Possession promisedmoved 24 months from the original
9 of 9Construction stages doneevery applicable stage filed complete
19 of 46Units unsoldnot recorded sold or booked
Jump to the 42 documents Report an error

SHUBH SANGAM is a Mixed Development project by SHUBH REALITIES in Rajkot, Gujarat, registered with GujRERA as PR/GJ/RAJKOT/RAJKOT/Others/MAA12343/EX1/EX2/290626/310527 on 29 Sep 2023. Possession is promised by 31 May 2027. The completion date has moved by 24 months from the original filing. 27 of the 46 units on this registration are recorded sold or booked, and 9 of 9 construction stages are filed complete.

At a glance

Project

  • NameSHUBH SANGAM
  • TypeMixed Development
  • Location
    • 80 40 FEET ROAD BESIDE RMC GARDEN
    • NEAR BPCL PETROL PUMP NEW RAILNAGAR
    • Rajkot
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/RAJKOT/RAJKOT/Others/MAA12343/EX1/EX2/290626/310527
  • ReraGenie IDRG-GJ-81913

Builder

  • NameSHUBH REALITIES
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredSep 2023First promiseMay 2025Revised toMay 2027

Key facts

Registration and timeline

  • StatusValid until 31 May 2027
  • Registered on29 Sep 2023
  • Promised completion31 May 2027
  • Revised completionRevised to 31 May 2027 (originally 31 May 2025)
  • Buildings1 building record
  • Documents filed42 files

Current status

59%27 of 46 units booked
100.0%Of the estimated cost spent so far

Figures as on 25 May 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1---252146

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 25 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 9 construction stages are filed complete.

1: 100% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 25 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyYes100%
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area683 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 3.80 cr
Cost incurredRs 3.80 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
1NARs 3.80 crRs 3.80 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMAITRI MODI
EngineerJIGNESH P KHERADIA

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/RAJKOT/RAJKOT/Others/MAA12343/EX1/030925/310526Applied Jul 2025; approved Sep 2025
PR/GJ/RAJKOT/RAJKOT/Others/MAA12343/EX1/EX2/290626/310527Applied May 2026; approved Jun 2026

Documents filed42

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/RAJKOT/RAJKOT/Others/MAA12343/EX1/EX2/290626/310527 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)25 May 2026
Engineer's certificate (Form 2)25 May 2026
Engineer's certificate annexure25 May 2026
Accountant's certificate (Form 3)25 May 2026
Site photograph, 125 May 2026
RERA registration certificate29 Sep 2023
Extension certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Rajkot

59%of this project is bookeddistrict median 56%
13%of Rajkot projects moved their completion datethis one moved by 24 months

Computed across the 1,800+ Rajkot projects on ReraGenie, from their own filings.

Keep SHUBH SANGAM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Rajkot1,800+ in Rajkot

2 kmSHUBH SANGAMOther 140Dot size: filed unitsN

Filed coordinates, straight-line distance. 140 registered projects within 2 km.

Builder: SHUBH REALITIES

SHUBH REALITIES has 2 registrations on GujRERA, including SHUBH SANGAM and SHUBH SANGAM-2. Read the full track record. See more projects on the Rajkot district page.

Frequently asked questions

What are my rights if SHUBH SANGAM is delayed beyond 31 May 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHUBH SANGAM?

The registered promoter entity is SHUBH REALITIES, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHUBH SANGAM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHUBH SANGAM?

The professionals named in the filing: Architect: MAITRI MODI; Engineer: JIGNESH P KHERADIA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHUBH SANGAM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHUBH SANGAM. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHUBH SANGAM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.