Home / Browse projects / Rajkot, Gujarat / SHREE SOMNATH RESIDENCY

Valid until 30 Apr 2020 Residential/Group Housing project

SHREE SOMNATH RESIDENCY

By BHARGAV DEVELOPERS

RG-GJ-91465 · RERA PR/GJ/RAJKOT/RAJKOT/Others/RAA01356/EX3/210120 · Last updated on GujRERA portal: 7 Sep 2020

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 3 extensions taken

Clear

  • Separate project account declared
Apr 2020Possession promisedmoved 12 months from the original
54 of 54Construction stages doneacross 6 buildings; every applicable stage filed complete
12 of 120Units unsoldnot recorded sold or booked
Jump to the 37 documents Report an error

SHREE SOMNATH RESIDENCY is a Residential/Group Housing project by BHARGAV DEVELOPERS in Rajkot, Gujarat, registered with GujRERA as PR/GJ/RAJKOT/RAJKOT/Others/RAA01356/EX3/210120 on 19 Jan 2018. Possession is promised by 30 Apr 2020. The completion date has moved by 12 months from the original filing. 108 of the 120 units on this registration are recorded sold or booked, and 54 of 54 construction stages are filed complete.

At a glance

Project

  • NameSHREE SOMNATH RESIDENCY
  • TypeResidential/Group Housing
  • Location
    • SHREE SOMNATH RESIDENCY APPARTMENT
    • RS NO. 28 PLOT NO. 43 TO 57 PAIKI 2
    • AT VILLAGE ANANDPAR (NAVAGAM)
    • Anandpar
    • Rajkot
    • 360003
  • Pincode360003
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/RAJKOT/RAJKOT/Others/RAA01356/EX3/210120
  • ReraGenie IDRG-GJ-91465

Builder

  • NameBHARGAV DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJan 2018First promiseApr 2019Revised toApr 2020

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2020
  • Registered on19 Jan 2018
  • Promised completion30 Apr 2020
  • Revised completionRevised to 30 Apr 2020 (originally 30 Apr 2019)
  • Buildings6 building records
  • Documents filed37 files

Current status

90%108 of 120 units booked
99.9%Of the estimated cost spent so far

Figures as on 7 Sep 2020, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING A---20020
WING B---20020
WING C---20020
WING D---20020
WING E---20020
WING F---20020

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 7 Sep 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

54 of 54 construction stages are filed complete across 6 buildings.

WING A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
WING B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
WING C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
WING D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
WING E100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
WING F100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 7 Sep 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes0%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyYes100%
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,729 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 5.28 cr
Cost incurredRs 5.28 cr
Spent of the estimate99.93%
BuildingWingEstimatedIncurred
WING ANARs 88.06 lakhRs 87.99 lakh
WING BNARs 88.06 lakhRs 87.99 lakh
WING CNARs 88.06 lakhRs 87.99 lakh
WING DNARs 88.06 lakhRs 87.99 lakh
WING ENARs 88.06 lakhRs 87.99 lakh
WING FNARs 88.06 lakhRs 87.99 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDEEPAK TRIVEDI
EngineerBIPIN ADHIYA

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/RAJKOT/RAJKOT/Others/RAA01356/EX1/150519Applied Apr 2019; approved May 2019
PR/GJ/RAJKOT/RAJKOT/Others/RAA01356/EX2/160819Applied Jul 2019; approved Aug 2019
PR/GJ/RAJKOT/RAJKOT/Others/RAA01356/EX3/210120Applied Jan 2020; approved Jan 2020

Documents filed37

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/RAJKOT/RAJKOT/Others/RAA01356/EX3/210120 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)7 Sep 2020
Engineer's certificate annexure7 Sep 2020
Accountant's certificate (Form 3)7 Sep 2020
Architect's certificate (Form 1)5 Sep 2020
RERA registration certificate19 Jan 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Rajkot

90%of this project is bookeddistrict median 56%
13%of Rajkot projects moved their completion datethis one moved by 12 months

Computed across the 1,800+ Rajkot projects on ReraGenie, from their own filings.

Keep SHREE SOMNATH RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Anandpar1,800+ in Rajkot

2 kmSHREE SOMNATH RESIDENCYOther 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 4 registered projects within 2 km.

Builder: BHARGAV DEVELOPERS

BHARGAV DEVELOPERS has 1 registration on GujRERA, including SHREE SOMNATH RESIDENCY. Read the full track record. See more projects on the Rajkot district page.

Frequently asked questions

What are my rights if SHREE SOMNATH RESIDENCY is delayed beyond 30 Apr 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHREE SOMNATH RESIDENCY?

The registered promoter entity is BHARGAV DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHREE SOMNATH RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHREE SOMNATH RESIDENCY?

The professionals named in the filing: Architect: DEEPAK TRIVEDI; Engineer: BIPIN ADHIYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE SOMNATH RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE SOMNATH RESIDENCY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE SOMNATH RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.